Provide Resident Engineering Sample Clauses

Provide Resident Engineering. The Construction Manager will work approximately 12 hours per day. It is assumed that the Construction Manager will be able to complete all daily project documentation in the course of the shift and that total on-site inspection time is anticipated to be 10 working days. It is assumed that the Contractor will work five (5) days a week during the construction period resulting in 10 working days. The following tasks will be performed during the course of a typical day's shift during construction: a. Review construction submittals, including shop drawings and materials proposed for use on the project, submitted by the Contractor for conformance with the project's Contract Documents. Submittals will either be approved, conditionally approved, or rejected and returned to the Contractor for their records and/or to make changes or revisions. The Engineer will prepare and maintain a submittal register to log the submittals received. The submittal register will include information on the submitted items including date received, date returned, and action taken, and will be made available to the Sponsor and Contractor upon request. b. Review copies of the survey data and other construction tasks for general compliance with the construction documents. c. Coordinate, review and provide a response to construction and general project Request for Information (RFIs). d. Prepare and process change orders. e. Conduct employee interviews and review Contractor's and subcontractor's weekly payroll records as required by the FAA. As part of this effort, all payrolls must be reviewed and logged when received. A log identifying current status of reviews and any action taken to correct noted discrepancies, will be provided for Sponsor review at time of Request for Reimbursement processing, as appropriate. f. Review and coordinate revisions by the Contractor for quality control and quality assurance testing firm submittals performed as part of the quality assurance testing required by the project specifications. g. Maintain record of the progress of construction and review the quantity records with the Contractor on a periodic basis. h. Prepare the periodic cost estimates and review the quantities with the Contractor. The Engineer, Sponsor and Contractor will resolve discrepancies or disagreements with the Contractor's records. The periodic cost estimate will also include all other costs associated with the project (administrative costs, engineering, any miscellaneous costs). After ...
AutoNDA by SimpleDocs
Provide Resident Engineering. The Construction Manager will work approximately 12 hours per day and the Field Engineer will work 10 hours per day. It is assumed that the Construction Manager and Field Engineer will be able to complete all daily project documentation in the course of the shift and that total inspection on-site time is anticipated to be 45 working days. In summary, the following personnel is proposed for 2020 and 2021, respectively: Construction Manager 30 15 45 Field Engineer 10 0 0 The following tasks will be performed during the course of a typical day’s shift during construction:  Reviewing and approving construction submittals, consisting of the plans and material submittal data received from the Contractor.  Review copies of the survey data and other construction tasks for general compliance with the construction documents.  Coordinate, review and provide a response to construction and general project Request for Information (RFI).  Prepare and process change orders.  Conduct employee interviews and review Contractor's and subcontractor’s weekly payroll records as required by the FAA. As part of this effort, all payrolls must be reviewed and logged when received. A log identifying current status of reviews and any action taken to correct noted discrepancies, will be provided for Sponsor review at time of Request for Reimbursement processing, as appropriate.  Review and coordinate revisions by the Contractor for quality control and acceptance testing firm submittals performed as part of the acceptance testing required by the project specifications.  Maintain record of the progress of construction and review the quantity records with the Contractor on a periodic basis.  Prepare the periodic cost estimates and review the quantities with the Contractor. The Engineer, Sponsor and Contractor will resolve discrepancies or disagreements with the Contractor’s records. The periodic cost estimate will also include all other costs associated with the project (administrative costs, engineering, any miscellaneous costs). After compiling all costs, the Engineer will then submit the periodic cost estimate to the Sponsor for payment.  Maintain daily logs of the construction activities for the duration of time on site which includes the Construction Project Daily Inspection Checklist as required by the Construction Safety and Phasing Plan and SPCD.  Prepare a weekly status report using the FAA's standard form. The report will be submitted to the Sponsor, the FAA and the of...
Provide Resident Engineering. The Construction Manager will be on-site full time and will work approximately 12 hours per day. It is assumed that the Construction Manager will be able to complete all daily project documentation in the course of their shift and that total inspection on-site time is anticipated to be 2 working days. Incidental travel costs, including vehicle usage, mileage, lodging, per diem, etc., are in addition to the engineering hours expended.  Review and approve construction submittals, consisting of the plans and material submittal data received from the Contractor.  Review copies of the survey data and other construction tasks for general compliance with the construction documents.  Coordinate, review and provide a response to construction and general project Request for Information (RFIs).  Prepare and process change orders.  Maintain record of the progress of construction and review the quantity records with the Contractor on a periodic basis.  Prepare the periodic cost estimates and review the quantities with the Contractor. The Engineer, Sponsor and Contractor will resolve discrepancies or disagreements with the Contractor’s records. The periodic cost estimate will also include all other costs associated with the project (administrative costs, engineering, any miscellaneous costs). After compiling all costs, the Engineer will then submit the periodic cost estimate to the Sponsor for payment.  Maintain daily logs of the construction activities for the duration of time on site which includes the Construction Project Daily Inspection Checklist. Verify that restricted areas, roads, staging areas, etc. are all remaining within the areas cleared under environmental documentation.  Conduct a final inspection that will check that the Contractor has removed all construction equipment and construction debris from the Airport, that all access points have been re-secured (fences repaired, gates closed and locked, keys returned, etc.) and the site is clean.

Related to Provide Resident Engineering

  • Engineering Forest Service completed survey and design for Specified Roads prior to timber sale advertisement, unless otherwise shown in A8 or Purchaser survey and design are specified in A7. On those roads for which Forest Service completes the design during the contract, the design quantities shall be used as the basis for revising estimated costs stated in the Schedule of Items and adjusting Timber Sale Account. (a) A7 to show Purchaser’s performance responsibility. (b) The Schedule of Items to include costs of survey and design, as provided under B5.24, and adjust Timber Sale Account, as provided in B5.

  • Geotechnical Engineer « »« » « » « » « » « »

  • Engineering Services Definition: Engineering Services includes any service or creative work, the adequate performance of which requires education, training and experience in the application of special knowledge in consulting, investigating, evaluating, planning and designing, engineering principles. Engineering Services covered by the Xxxxxx Architect-Engineers Act (40 U.S.C. 1102) are not covered in the primary scope of OASIS SB. Examples: Service areas that are included under the Engineering Services discipline include, but are not limited to the following: 1. Systems Engineering 2. Advanced Technology Pilots and Trials 3. Alternative Energy Sources and Engineering 4. Configuration Management 5. Concept Development

  • Engineer Resources The Engineer shall furnish and maintain quarters for the performance of all services, in addition to providing adequate and sufficient personnel and equipment to perform the services required under the contract. The Engineer certifies that it presently has adequate qualified personnel in its employment for performance of the services required under this contract, or it will be able to obtain such personnel from sources other than the State.

  • Information Systems Acquisition Development and Maintenance a. Client Data – Client Data will only be used by State Street for the purposes specified in this Agreement.

  • Reverse Engineering The Customer must not reverse assemble or reverse compile or directly or indirectly allow or cause a third party to reverse assemble or reverse compile the whole or any part of the software or any products supplied as a part of the Licensed System.

  • Project Development a. Collaborate with COUNTY and project clients to identify requirements and develop a project Scope Statement. a. Develop a Work Breakdown Structure (WBS) for each project. b. Evaluate Scope Statement to develop a preliminary cost estimate and determinate whether project be vendor bid or be executed under a Job Order Contract (JOC).

  • Architect/Engineer (A/E) means a person registered as an architect pursuant to Tex. Occ. Code Xxx., Chapter 1051, as a landscape architect pursuant to Tex. Occ. Code Xxx., Chapter 1052, a person licensed as a professional engineer pursuant to Tex. Occ. Code Xxx., Chapter 1001 and/or a firm employed by Owner or a design-build contractor to provide professional architectural or engineering services and to exercise overall responsibility for the design of a Project or a significant portion thereof, and to perform the contract administration responsibilities set forth in the Contract.

  • Design Development An interim step in the design process. Design Development documents consist of plans, elevations, and other drawings and outline specifications. These documents will fix and illustrate the size and character of the entire project in its essentials as to kinds of materials, type of structure, grade elevations, sidewalks, utilities, roads, parking areas, mechanical and electrical systems, and such other work as may be required.

  • Professional Engineering and Architect’s Services Professional Engineering and Architect’s Services are not permitted to be provided under this Agreement. Texas statutes prohibit the procurement of Professional Engineering and Architect’s Services through a cooperative agreement.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!