Completion Acceptance. B.1.1. The Contractor shall make every effort to deliver the Materials in accordance with the Specifications for acceptance by the Client.
B.1.2. When the Materials have been delivered to the Client for acceptance, the Client will subject these to an Acceptance test at his own expense and under his own responsibility during the acceptance period of one week. By accepting the Materials, the Client discharges the Contractor in respect of all its obligations concerning the Results.
B.1.3. If the Client does not reject the Materials (wholly or in part) within the period mentioned in paragraph 2, they shall be deemed to have been accepted and delivered.
B.1.4. The Client shall also be deemed to have accepted the Materials if the Client has started to use the Materials or if the Client has not informed the Contractor in writing, within ten days after delivery at the latest, that and for what reason he does not accept the Materials.
B.1.5. If Materials are not accepted, Contractor shall specify which adjustments will be made and the time or costs involved. The Client shall subsequently indicate whether he agrees to the said adjustments and the corresponding time and costs or whether he refrains from rejection. The Contractor will make every effort to remedy the Faults identified by the Client and reproducible within the period agreed by the parties and, in the absence thereof, within a reasonable period.
B.1.6. The implementation of adjustments following a rejection of a Material can take place on a production environment or on an acceptance environment. This is at the discretion of Contractor.
B.1.7. If the Client has accepted the Results (with the exception of Faults in functionalities and external appearance; minor Faults), the guarantee period of 30 days will commence. Within this period, the Results are deemed accepted, but Faults may be reported that could not reasonably have been discovered during the Acceptance Test. The Contractor will specify and supplement any Faults with the expected time and, if the Faults cannot be easily remedied within 30 days, any additional costs for modification of those parts. This guarantee period is therefore not an extended Acceptance Test and does not provide any more guarantees than those stipulated in this paragraph.
B.1.8. Minor Faults, including Faults which, by their nature and/or number, do not reasonably prevent the Commercial use of the Materials, shall not be a reason for withholding acceptance, without prejudice ...
Completion Acceptance. The Project Owner shall promptly organize completion acceptance as provided under the Contract.
Completion Acceptance. 31.1 The project has the completion acceptance conditions. The contractor shall provide the complete completion information and completion acceptance report to the contractor in accordance with the relevant provisions of the national project completion acceptance. If both parties agree that the contractor shall provide the completion plan, the date and copy shall be agreed in the special terms. Respectfully.
31.2 The Employer organizes the acceptance of the relevant unit within 28 days after receiving the completion acceptance report, and grants approval or proposes amendments within 14 days after the acceptance. The contractor makes amendments as required, and bears the costs of amendments caused by its own reasons.
31.3 The Employer does not organize the acceptance within 28 days after receiving the completion acceptance report sent by the contractor, or does not propose amendments within 14 days after acceptance, it is deemed that the completion acceptance report has been approved.
31.4 The completion acceptance of the project is passed, and the date on which the contractor submits the completion acceptance report is the actual completion date. If the project passes the completion acceptance after modification according to the requirements of the contractor, the actual completion date is the date that the contractor submits to the contractor for acceptance after modification.
31.5 The Employer will not organize acceptance within 28 days after receiving the Contractor’s Completion Acceptance Report, and will assume project storage and all accidental responsibilities from the 29th day.
31.6 The scope and completion time of the intermediate delivery project shall be agreed between the two parties in the special terms, and their acceptance procedures shall be handled in accordance with paragraphs 31.1 to 34 of this general clause.
Completion Acceptance. Party B provides the as-built drawing with qualified as-built acceptance data and safety information: Provide 4 sets of as-built drawings and as-built acceptance data to the construction unit within one month after the completion of the acceptance.
Completion Acceptance. Upon notice to the Contractor, the Owner shall have the right to take possession of and use for any purpose any partially completed portion of the Work. The taking of possession or use shall not be deemed to be the Owner's acknowledgement of completion and acceptance of that portion of the Work or the Owner's concurrence that such Work conforms to the Contract and shall not limit or waive the Contractor's responsibility with respect thereto pursuant to this Contract or otherwise. When the Contractor has completed the Work, or a component system thereof as defined in the Contract Documents ready to be turned over to the Owner for operation in accordance with the Work Schedule, it may give the Owner's Representative notice that the Work, or a component system thereof, has achieved Functional Completion. Within ____ Work Days of receipt of that notice, the Owner's Representative shall either issue a Functional Completion certificate or give notice to the Contractor of the reasons why the Work, or component system thereof, has not achieved Functional Completion. Neither certification by the Owner's Representative that the Work, or a component system thereof, has reached Functional Completion or the acceptance by the Owner of the Work, or a component system thereof, as being ready for operation shall relieve the Contractor of any of its obligations under this Contract, or otherwise. After the Contractor has completed all Work under this Contract and corrected all known deficiencies, it shall give the Owner's Representative notice that the Work has been finally completed. Within ___ Work Days of receipt of that notice, the Owner's Representative shall either issue a Final Completion Notice, or give notice to the Contractor of the deficiencies to be remedied before a Final Completion Notice can be issued. In the latter case, the foregoing procedure with respect to the deficiencies shall be repeated until the Owner's Representative issues the Final Completion Notice. Notwithstanding the foregoing, the Owner's issuance of the Final Completion Notice shall not relieve the Contractor of any of its obligations under this Contract, or otherwise. The parties agree that it is a condition precedent to the issuance of a Final Completion Notice and to the release of the holdback that the Contractor satisfy each of the following requirements: the Work has been fully completed in accordance with the terms and conditions of this Contract; all deficiencies with respect to the W...
Completion Acceptance. 1. Party B shall arrange Party A to carry out completion inspection to this project at least 10 days before the completion date stipulated hereof, and provide Party A the completion materials and completion inspection report approved by Party A at the same time.
2. If Party A finds any non-conformance in this project upon completion inspection, Party B shall make correction within 3 working days after receiving notice from Party A and arrange Party A for acceptance inspection again and pass it, and Party B shall bear all expenses arising therefrom; if Party B fails to make correction, arrange Party A for inspection again, or pass it as scheduled, for every delayed day, Party A is entitled to directly deduct 1% of the final project price.
3. After this project has passed the completion acceptance, Party B shall hand over relevant materials, equipment, documents, certificates etc. of this project, and as requested by Party A, to Party A.
Completion Acceptance. 18.1 Definition of completion acceptance
18.1.1 Completion acceptance shall mean the acceptance inspection done by the Project Owner as required by the Contract after completion of all Contract work by the Contractor.
18.1.2 State acceptance shall mean the acceptance done by relevant government authority in accordance with requirements of laws, regulations, codes and policies, with respect to the whole project fully organized and implemented by the Project Owner, before formal delivery and operation.
18.1.3 If the state acceptance is required, the completion acceptance shall be part of the state acceptance. Various acceptance and assessment criteria used for completion acceptance shall meet the national acceptance criteria. Various completion acceptance materials provided by the Project Owner and the Contractor for completion acceptance shall meet the national acceptance requirements.
Completion Acceptance. 8.2.1 According to industry standards, the relevant acceptance shall be conducted by the government’s environmental protection authority.
8.2.2 The acceptance shall be organized by the parent unit of the Employer.
8.2.3 The acceptance shall be organized by the Employer.
Completion Acceptance. Completion Acceptance Procedures Agreement on completion acceptance procedures:
Completion Acceptance. When the Project meets the conditions for completion acceptance, the Contractor shall provide complete as-built data and completion acceptance report to the Employer in accordance with relevant national regulations on the acceptance upon project completion. The Contractor shall provide the Employer with the as-built drawings in the copies and on the date as agreed. After the Employer’s representative receives and agrees on the completion acceptance report from the Contractor, the Contractor shall organize relevant departments to conduct acceptance within the time specified in the agreement, and shall give approval or put forward modification opinions within 5 days upon acceptance. The Contractor shall make such modification as required at his own cost if such modification is attributed to the Contractor.