Contractor’s Responsibility for Work Sample Clauses

Contractor’s Responsibility for Work. Until the Owner's final written acceptance of the entire completed work, or a designated portion thereof, the Contractor shall have the charge and care thereof and shall take every precaution against injury or damage to any part due to the action of the elements or from any other cause, whether arising from the execution or from the nonexecution of the work. The Contractor shall rebuild, repair, restore, and make good all injuries or damages to any portion of the work occasioned by any of the above causes before final acceptance and shall bear the expense thereof except damage to the work due to unforeseeable causes beyond the control of and without the fault or negligence of the Contractor, including but not restricted to acts of God such as earthquake, tidal wave, tornado, hurricane or other cataclysmic phenomenon of nature, or acts of the public enemy or of Government authorities. If the work is suspended for any cause whatever, the Contractor shall be responsible for the work and shall take such precautions necessary to prevent damage to the work. The Contractor shall provide for normal drainage and shall erect necessary temporary structures, signs, or other facilities at his/her expense. During such period of suspension of work, the Contractor shall properly and continuously maintain in an acceptable growing condition all living material in newly established planting, seedings, and soddings furnished under his/her contract, and shall take adequate precautions to protect new tree growth and other important vegetative growth against injury. Neither the final certificate of payment nor any provision in the Contract nor partial or entire use of the Improvements embraced in this contract by the Sponsor or the public shall constitute an acceptance of work not done in accordance with the Contract or relieve the Contractor of liability in respect to any express warranties or responsibility for faulty materials or workmanship. The Contractor shall promptly remedy any defects in the work and pay for any damage to other work resulting therefrom which appear within a period of twelve (12) months from the date of Substantial Completion of the work, unless otherwise stated in the Substantial Completion Notice(s) from Owner. 70-15 CONTRACTOR'S RESPONSIBILITY FOR UTILITY SERVICE AND FACILITIES OF OTHERS (Revised March 2007). As provided in the subsection titled RESTORATION OF SURFACES DISTURBED BY OTHERS of this section, the Contractor shall cooperate with the provid...
AutoNDA by SimpleDocs
Contractor’s Responsibility for Work. The Contractor’s responsibility will terminate when all work has been completed, the final inspection made, and the work accepted by the Contracting Officer. The Contractor will then be released from further obligation except as required by the warranties specified elsewhere in the contract.
Contractor’s Responsibility for Work. Until final acceptance of the work by VDOT in accordance with the requirements of this Section, the Contractor shall have charge and care thereof and shall take every precaution against damage to any part thereof by action of the elements or from any other cause. The Contractor shall rebuild, repair, restore, and make good on damage to any portion of the work occasioned by any of the foregoing causes before final acceptance and shall bear the expense thereof. The County may reimburse the Contractor for repair of damage to work attributable to unforeseeable causes beyond the control of and without the fault or negligence of the Contractor as determined by the Engineer. In case of suspension of work, the Contractor shall be responsible for the project and shall take such precautions as may be necessary to prevent damage to the work, provide for erosion control and drainage, and erect any necessary temporary structures, signs, or other facilities as determined by the Engineer. During the suspension of work, the Contractor shall properly and continuously maintain in an acceptable growing condition all living material in newly established plantings, seedings, and soddings furnished under the Contract and shall take adequate precautions to protect new tree growth and other important vegetation against damage.
Contractor’s Responsibility for Work. Delete the following from the first paragraph. “except as provided in Subsection 106.07”.
Contractor’s Responsibility for Work. Until the Department’s acceptance of the work under each work order, take charge and custody of the work, and take every necessary precaution against injury or damage to the work by the action of the elements or from any other cause whatsoever, arising either from the execution or from the nonexecution of the work. Rebuild, repair, restore, and make good, without additional expense to the Department, all injury or damage to any portion of the work occasioned by any of the above causes before its completion and acceptance, except that in case of extensive or catastrophic damage, the Department may, at its discretion, reimburse the Contractor for the repair of such damage due to unforeseeable causes beyond the control of and without the fault or negligence of the Contractor, including but not restricted to Acts of God, of the public enemy, or of governmental authorities.
Contractor’s Responsibility for Work. Until acceptance, the Work and all materials shall be under Contractor’s charge and care, and Contractor shall take every reasonable precaution against injury or damage to the Work or to any part thereof by the action of the elements or from any other cause whatsoever. Contractor shall rebuild, repair, restore and make good, at Contractor’s own expense, all injuries or damages to any portion of the Work occasioned by any of the above causes before its completion and acceptance.
Contractor’s Responsibility for Work. No removal work made under provision of this paragraph shall be done without lines and grades having been established by the RPR. Work done contrary to the instructions of the RPR, work done beyond the lines shown on the plans or as established by the RPR, except as herein specified, or any extra work done without authority, will be considered as unauthorized and will not be paid for under the provisions of the contract. Work so done may be ordered removed or replaced at the Contractor’s expense. Upon failure on the part of the Contractor to comply with any order of the RPR made under the provisions of this subsection, the RPR will have authority to cause unacceptable work to be remedied or removed and replaced; and unauthorized work to be removed and recover the resulting costs as a liquidated damage against the Contractor.
AutoNDA by SimpleDocs
Contractor’s Responsibility for Work. The Contractor shall be responsible for all work and for persons or entities engaged in work performed pursuant to this Agreement, including, but not limited to, contractors, subcontractors, suppliers, and providers of services. The Contractor shall be responsible for any and all disputes arising out of its contracts for work on the Project. Neither the State Water Board nor ABAG will mediate disputes between the Contractor and any other entity concerning responsibility for performance of work.
Contractor’s Responsibility for Work. Until the State formally accepts the work, the Contractor shall be liable for any injury or damage to any part of the work from the elements, except for an act of God as defined by California Public Contract Code section 10122(c) or a natural disaster as proclaimed by the State or Federal government), and damages that are directly and proximately occasioned by acts of the State or Federal government and the public enemy. No advertising of any description will be permitted in or about the work site except by order of the State.
Contractor’s Responsibility for Work. 13.1. Until the final acceptance of the work by the City in writing, Contractor shall have the charge and care thereof, and shall take every necessary precaution against injury or damage to any part thereof by the effects of the elements or from any other cause. Contractor, at its own expense, shall rebuild, repair, restore, and correct all injuries or damages to any portion of the work occasioned by any causes before its completion and acceptance. In case of suspension of work from any cause whatsoever, Contractor shall be responsible for all materials and shall properly store same, if necessary, and shall provide suitable drainage, barricades, and warning signs where necessary. Contractor shall correct or replace, at its own expense and as required by City, any material which may be destroyed, lost, damaged, or in any way made useless for the purpose and use intended by the contract documents, plans, and specifications prior to final acceptance of the work, or portions thereof. Contractor shall be relieved of the responsibilities provided in this section upon final acceptance of the work by City, except no such relief shall apply to damages or injuries caused by or related to actions of Contractor or its subcontractors.