Force Account Work Sample Clauses

Force Account Work. Work, ordered in writing by Metro, for which Contractor must report its actual costs in accordance with Section 8.4 of the General Conditions.
AutoNDA by SimpleDocs
Force Account Work. (a) A governmental unit shall secure prior written approval from the department for use of the force account method in lieu of contracts for any professional ser- vices or construction activities in excess of $10,000. (b) The department’s approval shall be based on the govern- mental unit’s verification and demonstration that it has the neces- sary competence required to accomplish such work and that the work can be accomplished more economically by the use of the force account method.
Force Account Work. 8.4.1 If Contractor does not respond to Metro's Request for Proposal with a cost breakdown within the fourteen (14)-day period as required above, or if Metro determines that Contractor's breakdown of costs is unreasonable in consideration of the Work proposed to be added or deleted, or if Metro determines that the proposed Work must be commenced promptly to avoid delay to the Project, Metro may issue an order for Force Account Work and Contractor shall promptly perform or delete the Work described in such order. Change, if any, in the Contract Amount due to such Force Account Work shall be the sum total of the following items: 8.4.1.1 Actual labor cost, including premium on worker’s compensation insurance and charge for social security taxes, and other taxes pertaining to labor. 8.4.1.2 The proportionate cost of premiums of public liability property damage and other insurance applicable to the extra Work involved and required by these Contract Documents. materials. 8.4.1.3 Actual cost of material, including applicable taxes pertaining to 8.4.1.4 Actual cost of plant and equipment rental, at rates to be agreed upon in writing before the Work is begun or at rates per Section 8.3.4 above. No charge for the cost of repairs to plant or equipment will be allowed. Equipment items having a capital cost of under $250.00 are considered small tools and classified as Overhead. 8.4.1.5 Overhead and Profit as provided and limited in Section 8.3. 8.4.1.6 The proportionate actual costs of premiums for bonds required by these Contract Documents. 8.4.2 Whenever any Force Account Work is in progress, each working day Contractor shall furnish to Metro a detailed written report signed by Contractor and Project Manager of the amount and cost of all of the items listed in (1) through (6) above, and no claim for compensation for such extra Work will be allowed unless such report shall have been made. Metro reserves the right to provide such materials as it may deem expedient, and no compensation, overhead, or profit will be allowed to Contractor for such materials.
Force Account Work. (a) A governmental unit or the Board of Regents shall secure prior written approval from the department for use of the force account method in lieu of contracts for any professional services or construction activities. (b) The department shall approve the use of force account work if the governmental unit or Board of Regents demonstrates to the department’s satisfaction that the governmental unit or Board of Regents has the necessary competence required to accomplish the work and that the work can be accomplished more economically by the use of the force account method. (c) The force account reimbursement for design and construc- tion services shall be based on the actual cost of services provided and departmental reimbursement for such costs may not exceed 5 percent of the total project reimbursement when bond−sourced funds are used. History: CR 00−025: cr. Register September 2002 No. 561, eff. 10−1−02; CR 09−112: am. (3) (b), r. and xxxx. (4), x. (5) Register December 2010 No. 660, eff. 1−1−11; 2015 Wis. Act 330 s. 20: am. (2), (4) (a), (b) Register April 2016 No. 724, (1) RUNOFF MANAGEMENT GRANT AGREEMENTS. (a) State cost− share funds may be used to share in the actual cost required for the installation of eligible urban best management practices identified in runoff management grant agreements described in s. NR 155.21.
Force Account Work. (a) A governmental unit or the board of regents shall secure prior written approval from the de- partment for use of the force account method in lieu of contracts for any professional services or construction activities in excess of $35,000. (b) The department shall approve the use of force account work if the governmental unit or board of regents demonstrates to the department’s satisfaction that the governmental unit or board of regents has the necessary competence required to accomplish the work and that the work can be accomplished more economi- cally by the use of the force account method.
Force Account Work. If no agreement can be reached on Changes in the Work and adjustment of the Work Order Package Price or Work Order Package Deadline, or the Design- Builder refuses to accept a Change Notice, Change Order, or Time and Material Change Order, the City shall have the right to have the Work in question done by Persons other than the Design-Builder.
Force Account Work. A Force Account may be used at the County’s discretion and only when either 1) agreement on the valuation of a change cannot be made using the methods described in the preceding paragraph, County Ordered Changes in the Work, or 2) the County cannot firmly establish an applicable and acceptable estimate for the cost of the Work because the level of effort necessary to perform and complete the Work cannot be reasonably estimated or anticipated but can only be determined by performing the Work. Because of the significant burden on the County to monitor and control the Work, Force Account Work is not a preferred method, and it shall be the responsibility of the Contractor to provide all necessary documentation and justification of costs. The rates for labor, equipment and materials to be used in cases of Work performed on a force account basis will be compensated as documented below. No costs other than those explicitly listed below shall be allowed: a. Labor: Before any Force Account Work begins, the Contractor shall submit for approval to the Project Officer the proposed hourly rates and associated labor costs (benefits and payroll burden) for all laborers and forepersons to be engaged in the Work. The number of laborers and forepersons engaged in the Work will be subject to regulation by the Project Officer and shall not exceed the number that the Project officer deems most practical and economical for the Work. For all labor and forepersons in direct charge of the force account Work, excluding general superintendence, compensation will be as follows: 1) Certified Pay Rate: The Contractor will receive the actual rate of wage or scale as set forth in his most recent payroll for each classification of laborers, and forepersons who are in direct charge of the specific operation. The time allowed for payment will be the number of hours such Workers are actually engaged in the Work. If overtime Work is authorized by the County, payment will be at the normal overtime rate set forth in the Contractor’s most recent payroll.
AutoNDA by SimpleDocs
Force Account Work. If an order to change Work, deletes Work that is to be performed hereunder and such deletion results in a substantial reduction, in the opinion of Company, in the labor or materials to be furnished by Contractor hereunder then such reduction in Work shall be considered "Omitted Work" and Company shall be entitled to a reduction in the compensation to be paid Contractor as provided in Article 18.
Force Account Work. The Materials, Equipment and labor rates and procedures established in this Section apply to Extra Work ordered by the Engineer to be performed as Force Account Work. A. Extra Work on a Force Account Basis - Before ordering Force Account Work, the Engineer will discuss the proposed work with the Contractor, and will seek the Contractor's comments and advice concerning the formulation of Force Account Work specifications. The Engineer is not bound by the Contractor's comments and advice, and has final authority to: determine and direct the Materials, Equipment and labor to be used on the approved Force Account Work and to determine the time of the Contractor's performance of the ordered Force Account Work. B. If the Engineer orders the performance of Extra Work as Force Account Work, the Engineer will record, on a daily basis, the Materials, Equipment, labor, and Special Services used for the Force Account Work during that day. The Engineer and the Contractor shall sign the record daily to indicate agreement on the Materials, Equipment, labor, and Special Services used for the Force Account Work performed on that day. C. The Owner will not be responsible for additional costs that are a direct or indirect result of the Contractor's inefficient means and methods or that reasonably could have been avoided if the Materials, Equipment, labor or services had been obtained at a more commercially reasonable cost. D. Payment for Force Account Work shall be negotiated and agreed upon by Change Order. DATE: October 21, 2024 PAGES: Addendum No. 1 (1 page) Acknowledge receipt of this Addendum by inserting its number and date on the Bid Form. Failure to do so may subject bidder to disqualification. This Addendum forms a part of the Contract Documents. It modifies the Contract Documents as follows: 1. IB-17.06 Delete the anticipated schedule in its entirety and replace with the following anticipated schedule: Bids Due - November 5, 2024 Anticipated Notice of Intent to Award – November 6, 2024 Anticipated City Council Approval – November 20, 2024 Anticipated Award Date and Notice to Proceed – November 22, 2024 Substantial Completion – June 30, 2025 Final Completion – July 31, 2025 2. BF-4.03 Delete Section 4.03 in its entirety to remove incentive language in its entirety. 3. Agreement Between Owner and Contractor - 4.02 Revise Section 4.02(A)(B) removing any and all incentive language and amounts and changing the substantial completion date of the Work to June 30, 2025 and...
Force Account Work. (a) A governmental unit or the Board of Regents shall secure prior written approval from the department for use of the force account method in lieu of contracts for any professional services or construction activities. (b) The department shall approve the use of force account work if the governmental unit or Board of Regents demonstrates to the department’s satisfaction that the governmental unit or Board of Regents has the necessary competence required to accomplish the work and that the work can be accomplished more economically by the use of the force account method. (c) The force account reimbursement for design and construc- tion services shall be based on the actual cost of services provided and departmental reimbursement for such costs may not exceed 5 percent of the total project reimbursement when bond−sourced funds are used. (1) RUNOFF MANAGEMENT GRANT AGREEMENTS. (a) State cost− share funds may be used to share in the actual cost required for the installation of eligible urban best management practices identified in runoff management grant agreements described in s. NR 155.21.