Request for Extension of Time Sample Clauses

Request for Extension of Time. If the performance of any act required of Consultant is directly prevented or delayed by reason of strikes, lockouts, labor disputes, unusual governmental delays, acts of God, fire, floods, epidemics, freight embargoes, or other causes beyond the reasonable control of the Consultant, as determined by the City, Consultant shall be excused from performing that act for the period of time equal to the period of time of the prevention or delay. In the event Consultant claims the existence of such a delay, the Consultant shall notify the City's Contract Administrator, or designee, in writing of that fact within ten calendar days after the beginning of any such claimed delay. Extensions of time will not be granted for delays to minor portions of work unless it can be shown that such delays did or will delay the progress of the work.
AutoNDA by SimpleDocs
Request for Extension of Time. In the event the Subcontractor's performance of this Subcontract is delayed or interfered with by acts of the Owner, Contractor or other subcontractors, it may request an extension of time for the performance of same, as hereinafter provided, but shall not be entitled to any increase in the Subcontract price or to damages or additional compensation as a consequence of such delays. If a progress schedule is furnished by Contractor to Subcontractor, it shall be solely for Contractor's benefit; however, Subcontractor must be ready to perform at the times indicated in the progress schedule. The Contractor makes no representation that it will be ready for the Subcontractor at the times indicated in said schedule regardless of whether delays may be occasioned by circumstances within the control of the Contractor. As required by the Contractor, the Subcontractor shall submit to the Contractor progress schedules for the work subcontracted, or at the Contractor's election, cooperate in the preparation of a progress schedule. DRAFT No allowance of an extension of time, for any cause whatever, shall be claimed by the Subcontractor or be made to it, unless the Subcontractor shall have made written request upon the Contractor for such extension within forty‐eight hours after the cause for such extension occurred and unless the Contractor and Subcontractor have agreed in writing upon the allowance of additional time to be made. If such extension of time is requested as aforesaid and Contractor and Subcontractor cannot agree thereupon, the Owner's Representative shall determine by certificate in writing what, if any, extension of time shall be allowed. No allowance of an extension of time shall in any event be made to the Subcontractor for delay by the Subcontractor in preparing drawings or in securing approval of the Owner's Representative thereto when such drawings are not properly prepared or when the Subcontractor by the exercise of reasonable diligence and judgment could have anticipated and avoided the delay. If Owner, with or without cause, shall terminate the General Contract or shall stop or suspend work under the General Contract, or if Owner shall fail to pay when due any sum payable under the General Contract, Contractor may order Subcontractor to stop or suspend work hereunder, and Contractor shall be liable to Subcontractor for any such stoppage or suspension only if and to the extent that Owner shall be liable to Contractor therefor. Contractor will pay to...
Request for Extension of Time. 1. Before the Project Manager acts on the Contractor's request for time extension, the Contractor must submit a written application to the Project Manager within ten (10) days after commencement of the condition that allegedly has caused the delay, with the following information: (a) the Contractor and Project description; (b) liquidated damage assessment rate, as specified in the contract; (c) original bid amount; (d) the original contract start date and completion date; (e) any previous time extensions granted (number and duration); (f) the extension of time requested; (g) the application for extension of time shall set forth in detail: (1) the nature of each alleged cause of delay in completing the Work; (2) the date upon which each such cause of delay began and ended and the number of days attributable to each such cause; (3) a statement that the Contractor waives all claims except for those delineated in the application and the particulars of any claims which the Contractor does not agree to waive. For time extensions for substantial and final completion payments, the application shall include a detailed statement of the dollar amounts of each element of claim item reserved; and (4) a statement indicating the Contractor's understanding that the time extension is granted only for purposes of permitting continuation of contract performance and payment for Work performed and that the City retains its right to conduct an investigation and assess liquidated damages as appropriate in the future.
Request for Extension of Time. 18.1. If the Contractor is delayed at any time in the commencement or progress of the Detailed Scope of Work by an act or neglect of the NJPA Member or Project Manager, or of an employee of either, or of a separate contractor employed by the NJPA Member, or by changes ordered in the Work, or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other causes beyond the Contractor’s control, or by other causes which the Project Manager determines may justify delay, then the Work Order Completion Time shall be extended for such reasonable time as the Project Manager may determine. 18.2. The Contractor agrees to make no claim for damages for the delay in the performance of any Work Order occasioned by any act or omission to act of the NJPA Member, Project Manager or any of their representatives, and agrees that any such claim shall be fully compensated for by an extension of time as provided herein.
Request for Extension of Time. In support of its request for an extension of time to complete this project, Norfolk Southern Railway Company (“Norfolk Southern”) states:
Request for Extension of Time. ‌ 18.1. If the Contractor is delayed at any time in the commencement or progress of the Detailed Scope of Work by an act or neglect of the Sourcewell Member or Project Manager, or of an employee of either, or of a separate contractor employed by the Sourcewell Member, or by changes 18.2. The Contractor agrees to make no claim for damages for the delay in the performance of any Purchase Order occasioned by any act or omission to act of the Sourcewell Member, Project Manager or any of their representatives, and agrees that any such claim will be fully compensated for by an extension of time as provided herein.
Request for Extension of Time. The Contractor agrees to supply, as soon as such data are available, any reasonable proof that is required by SFMTA to decide on any request for an extension of time. SFMTA shall examine the request and any documents supplied by the Contractor and shall determine if the Contractor is entitled to an extension of time and the duration of such extension. SFMTA shall notify the Contractor of its decision in writing. The granting of an extension of time because of Unavoidable Delays shall in no way operate as a waiver on the part of the City of the right to collect liquidated damages for other delays or of any other rights to which the City is entitled.
AutoNDA by SimpleDocs

Related to Request for Extension of Time

  • Request for Extension Upon request, the Department may extend the time allowed for both a response to the Letter of Concern and a Corrective Action Plan depending upon the nature of the deficiency. The Provider shall request an extension of time in writing from the Department’s designated representative. The written request shall contain a justification and proposed extension period.

  • Requests for Extension The Borrower may, by notice to the Administrative Agent (who shall promptly notify the Lenders) not earlier than 90 days and not later than 35 days prior to an anniversary of the Closing Date (each, an “Applicable Anniversary Date”), request that each Lender extend such Lender’s Maturity Date for an additional year from the Maturity Date then in effect for such Lender hereunder (such Lender’s “Existing Maturity Date”). The Borrower may request such an extension no more than two times.

  • Extension of Time If the Executive shall be in violation of any provision of this Article 6, then each time limitation set forth in this Article 6 shall be extended for a period of time equal to the period of time during which such violation or violations occur. If the Company seeks injunctive relief from such violation in any court, then the covenants set forth in this Article 6 shall be extended for a period of time equal to the pendency of such proceeding including all appeals by the Executive.

  • Extension of Time; Waiver At any time prior to the Effective Time, the parties may, by action taken or authorized by their respective Boards of Directors, to the extent permitted by applicable Law, (a) extend the time for the performance of any of the obligations or acts of the other parties, (b) waive any inaccuracies in the representations and warranties of the other parties set forth in this Agreement or any document delivered pursuant hereto or (c) subject to applicable Law, waive compliance with any of the agreements or conditions of the other parties contained herein; provided, however, that after the Company Stockholder Approval has been obtained, no waiver may be made that pursuant to applicable Law requires further approval or adoption by the Stockholders without such further approval or adoption. Any agreement on the part of a party to any such waiver shall be valid only if set forth in a written instrument executed and delivered by a duly authorized officer on behalf of such party. No failure or delay of any party in exercising any right or remedy hereunder shall operate as a waiver thereof, nor shall any single or partial exercise of any such right or power, or any abandonment or discontinuance of steps to enforce such right or power, or any course of conduct, preclude any other or further exercise thereof or the exercise of any other right or power. The rights and remedies of the parties hereunder are cumulative and are not exclusive of any rights or remedies which they would otherwise have hereunder.

  • Notice of Extension (a) If the Property Trustee is the only registered holder of the Debentures at the time the Company selects an Extended Interest Payment Period, the Company shall give written notice to the Administrative Trustees, the Property Trustee and the Trustee of its selection of such Extended Interest Payment Period two Business Days before the earlier of (i) the next succeeding date on which Distributions on the Trust Securities issued by the Trust are payable; or (ii) the date the Trust is required to give notice of the record date, or the date such Distributions are payable, to The Nasdaq National Market or other applicable self-regulatory organization or to holders of the Preferred Securities issued by the Trust, but in any event at least one Business Day before such record date. (b) If the Property Trustee is not the only holder of the Debentures at the time the Company selects an Extended Interest Payment Period, the Company shall give the holders of the Debentures and the Trustee written notice of its selection of such Extended Interest Payment Period at least two Business Days before the earlier of (i) the next succeeding Interest Payment Date; or (ii) the date the Company is required to give notice of the record or payment date of such interest payment to The Nasdaq National Market or other applicable self-regulatory organization or to holders of the Debentures. (c) The quarter in which any notice is given pursuant to paragraphs (a) or (b) of this Section 4.2 shall be counted as one of the 20 quarters permitted in the maximum Extended Interest Payment Period permitted under Section 4.1.

  • Extension of Time, Waiver, Etc At any time prior to the Effective Time, any party may, subject to applicable Law, (a) waive any inaccuracies in the representations and warranties of any other party hereto, (b) extend the time for the performance of any of the obligations or acts of any other party hereto or (c) waive compliance by the other party with any of the agreements contained herein or, except as otherwise provided herein, waive any of such party’s conditions. Notwithstanding the foregoing, no failure or delay by the Company, Parent or Merger Sub in exercising any right hereunder shall operate as a waiver thereof nor shall any single or partial exercise thereof preclude any other or further exercise thereof or the exercise of any other right hereunder. Any agreement on the part of a party hereto to any such extension or waiver shall be valid only if set forth in an instrument in writing signed on behalf of such party.

  • Extension of time for completion (i) Without prejudice to any other provision of this Agreement for and in respect of extension of time, the Contractor shall be entitled to extension of time in the Project Completion Schedule (the “Time Extension”) to the extent that completion of any Project Milestone is or will be delayed by any of the following, namely: (a) delay in providing the Right of Way of Construction Zone, environmental clearances or approval of railway authorities, specified in Clause 3.1 (iv); (b) Change of Scope (unless an adjustment to the Scheduled Completion Date has been agreed under Article 13); (c) occurrence of a Force Majeure Event; (d) any delay, impediment or prevention caused by or attributable to the Authority, the Authority's personnel or the Authority's other contractors on the Site; and (e) any other cause or delay which entitles the Contractor to Time Extension in accordance with the provisions of this Agreement. (ii) The Contractor shall, no later than 15 (fifteen) business days from the occurrence of an event or circumstance specified in Clause 10.5 (i), inform the Authority’s Engineer by notice in writing, with a copy to the Authority, stating in reasonable detail with supporting particulars, the event or circumstances giving rise to the claim for Time Extension in accordance with the provisions of this Agreement. Provided that the period of 15 (fifteen) business days shall be calculated from the date on which the Contractor became aware, or should have become aware, of the occurrence of such an event or circumstance. Provided further that notwithstanding anything to the contrary contained in this Agreement, Time Extension shall be due and applicable only for the Works which are affected by the aforesaid events or circumstances and shall not in any manner affect the Project Completion Schedule for and in respect of the Works which are not affected hereunder. (iii) On the failure of the Contractor to issue to the Authority’s Engineer a notice in accordance with the provisions of Clause 10.5 (ii) within the time specified therein, the Contractor shall not be entitled to any Time Extension and shall forfeit its right for any such claims in future. For the avoidance of doubt, in the event of failure of the Contractor to issue notice as specified in this clause 10.5 (iii), the Authority shall be discharged from all liability in connection with the claim. (iv) The Authority’s Engineer shall, on receipt of the claim in accordance with the provisions of Clause 10.5 (ii), examine the claim expeditiously within the time frame specified herein. In the event the Authority’s Engineer requires any clarifications to examine the claim, the Authority’s Engineer shall seek the same within 15 (fifteen) days from the date of receiving the claim. The Contractor shall, on receipt of the communication of the Authority’s Engineer requesting for clarification, furnish the same to the Authority’s Engineer within 10 (ten) days thereof. The Authority’s Engineer shall, within a period of 30 (thirty) days from the date of receipt of such clarifications, forward in writing to the Contractor its determination of Time Extension. Provided that when determining each extension of time under this Clause 10.5, the Authority’s Engineer shall review previous determinations and may increase, but shall not decrease, the total Time Extension. (v) If the event or circumstance giving rise to the notice has a continuing effect: (a) a fully detailed claim shall be considered as interim; (b) the Contractor shall, no later than 10 (ten) days after the close of each month, send further interim claims specifying the accumulated delay, the extension of time claimed, and such further particulars as the Authority’s Engineer may reasonably require; and (c) the Contractor shall send a final claim within 30 (thirty) days after the effect of the event or the circumstance ceases. Upon receipt of the claim hereunder, the Authority’s Engineer shall examine the same in accordance with the provisions of Clause 10.5 (iv) within a period of 30 (thirty) days of the receipt thereof

  • Extension of Agreement Prior to the original expiration date of this Agreement, the Parties mutually agree to extend this Agreement to the February 15 extension date identified in Paragraph VIII(A). The Parties acknowledge that no further extensions of this Agreement are authorized.

  • Delays and Extension of Time If the Contractor is delayed at any time in the progress of providing goods and/or services by an act or neglect of the District, or by changes ordered in the work, or by labor disputes, strikes, insurrections, fire, acts of God; unusual but well documented and excusable delays in performance, or other causes beyond the Contractor’s control, or by delay authorized by the District, then the contract Term of service may be extended by a contract amendment for such reasonable time as the District and the Contractor may agree.

  • Expiration and Extension of the Offer (i) Unless the Offer is extended pursuant to and in accordance with this Agreement, the Offer shall expire at midnight, New York Time, on the date that is twenty (20) Business Days after the date the Offer is first commenced (within the meaning of Rule 14d-2 promulgated under the Exchange Act) (as such date and time may be extended, the “Expiration Time”). In the event that the Offer is extended pursuant to and in accordance with this Agreement, then the Offer shall expire on the date and at the time to which the Offer has been so extended. (ii) Notwithstanding the provisions of Section 2.1(d)(i) or anything to the contrary set forth in this Agreement: (A) Acquisition Sub shall extend the Offer for any period required by any Law or Order, or any rule, regulation, interpretation or position of the SEC or its staff or NASDAQ, in any such case that is applicable to the Offer; (B) in the event that any of the conditions to the Offer set forth on Annex A, other than the Minimum Condition, are not satisfied or waived (if permitted hereunder) as of any then scheduled expiration of the Offer, Acquisition Sub shall extend the Offer for successive extension periods of ten (10) Business Days each (or any longer period as may be approved in advance by the Company) in order to permit the satisfaction of all of the conditions to the Offer; and (C) in the event that all of the conditions to the Offer set forth on Annex A have been satisfied or waived (if permitted hereunder), except that the Minimum Condition has not been satisfied, as of any then scheduled expiration of the Offer, Acquisition Sub shall extend the Offer for an extension period of ten (10) Business Days (or any longer period as may be approved in advance by the Company), it being understood and agreed that Acquisition Sub shall not be required to extend the Offer pursuant to this clause (C) on more than two (2) occasions, but may, in its sole discretion, elect to do so; provided, however, that the foregoing clauses (A), (B) or (C) of this Section 2.1(d)(ii) shall not be deemed to impair, limit or otherwise restrict in any manner the right of the parties to terminate this Agreement pursuant to the terms of Article IX, and in no event shall Acquisition Sub be required to extend the Offer beyond the Termination Date. (iii) Neither Parent nor Acquisition Sub shall extend the Offer in any manner other than pursuant to and in accordance with the provisions of Section 2.1(d)(ii) without the prior written consent of the Company. (iv) Neither Parent nor Acquisition Sub shall terminate or withdraw the Offer prior to the then scheduled expiration of the Offer unless this Agreement is validly terminated in accordance with Article IX, in which case Acquisition Sub shall (and Parent shall cause Acquisition Sub to) irrevocably and unconditionally terminate the Offer promptly (but in no event more than one (1) Business Day) after such termination of this Agreement.