Program Schedule Sample Clauses

Program Schedule. The Developer must attach as Exhibit C to this Agreement a Program Schedule, which is a timetable that the Developer must follow in developing the property to meet an NSP eligible end use. The Developer must submit performance reports as required by the Authority to demonstrate compliance with the Program Schedule. Changes to the schedule may be approved by the Authority only because of delays resulting from Acts of God or other delays that are not caused in any way by the Developer. It is the responsibility of the Developer to notify the Authority promptly in writing whenever a delay is anticipated or experienced.
AutoNDA by SimpleDocs
Program Schedule. The Contractor shall develop and maintain a Master Phasing Schedule and Detailed Program Schedules. The Master Phasing Schedule shall clearly identify all key milestones including all hardware, software, and data deliveries, all customer furnished items and the date required, major technical and programmatic reviews, and all TerreStar milestones that are dependent on S-BSS deliveries. The Detailed Program Schedules shall be used by the contractor to plan all tasks, task dependencies, and critical path. The Detailed Program Schedules shall be updated monthly to reflect program progress and provided to the TerreStar PMO with the monthly status report.
Program Schedule. The Grantee must inform HUD immediately, in writing, of any problems, delays or adverse conditions that will impair materially the Grantee’s ability to comply with the Program Schedule, and include a statement of action taken, or proposed to be taken, and any assistance needed to resolve the situation. HUD must approve any proposed changes to the Program Schedule that would modify any date or time period.
Program Schedule. A. Contractor shall conduct one (1) annual inspection within the first month after award of the Contract and within the first month of each renewal year thereafter. Contractor shall conduct one (1) semi-annual inspection within six (6) months after award of the Contract. B. Contractor must notify OC Public Works/Facilities Operation’s HVAC Shop Planner or Craft Supervisor a minimum of 72 hours in advance to schedule the P.M. inspection.
Program Schedule. Only Work Package 1a-1/3 and Work Package 1a-2 are scheduled to be completed and issued for proposals/bidding before the end of 2011 with construction proceeding in early 2012. As these facilities are constructed and made operational, and as future funding becomes available, IID will determine which elements of the remaining phases (Phases 1b and 2) will be required and/or if other elements such as additional system automation will be employed.
Program Schedule. The Contractor shall update the Master Schedule with Chipset tasks/milestones and shall develop and maintain Detailed Chipset Program Schedules. The Master Schedule shall clearly identify all key milestones including all hardware, software, and data deliveries, all TerreStar-furnished items and the date required, all deliveries to the terminal vendor and the date required, and major technical and programmatic reviews. The Detailed Program Schedules shall be used by the contractor to plan all tasks, task dependencies, and critical path. The Detailed Program Schedules shall be updated monthly to reflect program progress and provided to the TerreStar PMO with the monthly status report. The Contractor may maintain a separate Master Schedule for the Chipset development, however, the program interdependencies between the S-BSS development and the Chipset development shall be contained in each schedule.
Program Schedule. The GEC shall update and maintain the existing program schedule using Primavera P6 or more current version as specified by the STATE. The GEC shall maintain the schedule for key milestones and critical path for the duration of the program from information provided by others. The GEC shall include each individual project under development on the corridor by the STATE or other entities. The GEC shall depict the order and interdependence of various tasks, subtasks, milestones and deliverables. The GEC shall indicate the primary functional area, such as design, environmental, public involvement, right-of-way/utility, general administration, etc. for each activity. The GEC shall indicate when another party is responsible for completion of an activity such as review by the State. The GEC shall maintain the program schedule from execution through GEC contract completion. The GEC shall review progress during program- and project-level coordination meetings and update the schedule as necessary. The GEC shall identify issues that need resolution or action items in the Progress Report and in program- and project-level coordination meetings. The GEC shall produce a table of deliverables from the information provided in the schedules upon the request of the STATE. The GEC shall review, assess, monitor, and update monthly detailed schedules and other scheduling documents produced by others including utility companies and third party agencies, and shall integrate critical milestone elements within the program master schedule.
AutoNDA by SimpleDocs
Program Schedule. (A) The schedule of Demolition Activities as included in Exhibit F of the Grantee's HUD-approved HOPE VI Demolition Grant Application shall constitute the schedule that the Grantee will abide by in carrying out Demolition Activities ("Program Schedule"). (B) The Program Schedule must reflect the requirement that the Grantee will complete the Demolition Activities within two years from the date of execution of this Grant Agreement. (C) The Grantee must inform HUD immediately, in writing, of any problems, delays, or adverse conditions that will impair materially the Grantee's ability to comply with the Program Schedule, and include a statement of action taken, or proposed to be taken, and any assistance needed to resolve the situation. (D) The Grantee must request HUD approval of any proposed changes to the Program Schedule that would modify any date or time period in excess of 30 calendar days from the date previously approved by HUD. (E) If the Grantee does not comply with the reasonable time periods established by HUD under (B) above, HUD shall, in accordance with section 24(i) of the 1937 Act, and unless otherwise approved by HUD, recapture any grant funds not obligated by the Grantee and redistribute such funds to one or more other applicants eligible for HOPE VI demolition assistance, or to one or more other entities capable of proceeding expeditiously in the same locality in carrying out the Grantee's Demolition Plan. (F) If the Grantee fails to comply with the reasonable time periods established in (B) above, HUD may take into account whether factors beyond the Grantee's control are the cause of the delay.
Program Schedule. 7.1.1. Brocade shall deliver the Deliverables and perform the obligations as set forth in this PA12 in accordance with the Milestone Schedule, Attachment A. 7.1.2. HP shall deliver the supporting deliverables set forth in this PA12, in accordance with the Milestone Schedule, Attachment A. Any program slips by either party must be agreed upon in writing by HP and Brocade. 7.1.3. Any program schedule changes resulting from the normal program development cycle must be agreed upon in writing by HP and Brocade. Both parties will use good faith and due diligence to ensure proactive notification of potential program slips prior to major program milestones as defined by the Milestone Schedule, Attachment A.
Program Schedule. 8.1 The Contractor will by October 29, 2010 submit a program schedule (the “Program Schedule”) for review by the Province’s Representative. 8.2 The Program Schedule will be an overall schedule for the Program and will include information reasonably required by the Province for the Progress Monitor to fulfil his or her role under Article 12. The Contractor will ensure that the Program Schedule will meet all applicable requirements of this Agreement. 8.3 The Contractor will submit an updated Program Schedule at a maximum interval of 1 week, reflecting progress to date and changes to the dates identified in the Program Schedule, and include a comparison to the previously submitted Program Schedule.
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!