Project Schedule Updates Sample Clauses

Project Schedule Updates. Developer shall update the approved Project Schedule to reflect the current status of the Project and submit to TxDOT for review the proposed Project Schedule Update in accordance with Section 6.3 of the Agreement. The Project Schedule Update(s) shall include Developer's detailed schedule for executing the Work and all information and reporting required for the Project Schedule, and shall include only resources actually available to Developer. The Project Schedule Update(s) shall minimally include the following current Work data:
AutoNDA by SimpleDocs
Project Schedule Updates. During performance of the Initial Scope of Work, Developer shall be responsible for preparing and submitting to TxDOT monthly Schedule Updates of the approved Project Schedule for the Initial Scope of Work, as more particularly provided in Exhibit G to this Agreement. After completion of the Initial Scope of Work, Developer shall be responsible for submitting Schedule Updates on a quarterly basis.
Project Schedule Updates. Construction Manager shall update the Project Schedule (including a two-week look-ahead schedule) on a regular basis, but not less than one (1) time per month to assure maximum utilization of all Trade Contractors. All revisions and updates to the Project Schedule shall be approved by Owner.
Project Schedule Updates. The Contractor shall maintain the Project Schedule and update the Project Schedule monthly and whenever information indicates that a significant change in the Project Schedule is indicated, and provide a copy of each such update to Remediation Manager and Client. Contractor shall create the schedule in Microsoft Project or a compatible program acceptable to Client. The updates to the Project Schedule shall indicate the resources expended and percentage complete on each task, the status of all milestones and critical path activities, the delivery and allocation of materials and equipment, the delivery of various design documents for review and approval, and appropriate measures of the Contractor’s progress of its work. If an update to the Project Schedule indicates that the Project will not achieve milestones, or that critical path items have been delayed or not met, the Contractor shall evaluate the causes for such matters and prepare, in consultation with the Remediation Manager and any subcontractors, a written recommendation to Client for corrective measures.
Project Schedule Updates. The Landlord will ensure that the Project Schedule is at all times an accurate, reasonable and realistic representation of Landlord's plans for the completion of the Project in accordance with the requirements of this Agreement. The Landlord will, as required from time to time until Substantial Completion, but no less than once per calendar month, deliver an updated Project Schedule to VCHA’s Project Leader for review for compliance with the requirements of this Agreement, and which will include the following:
Project Schedule Updates. (a) Developer shall use Best Efforts to adhere to, and will instruct and use its Best Efforts to cause the Executive Construction Manager, the Project Architect and other Consultants and all contractors to adhere to, the dates and time periods set forth in the Schedule (subject to Force Majeure events, Coach Change Delays extending beyond the Change Order Grace Period resulting from any change requested by the Coach Member and Coach Work Delays).
Project Schedule Updates. (i) PE Member hereby approves the Schedule, in the form agreed by the Parties and dated as of the date hereof.
AutoNDA by SimpleDocs

Related to Project Schedule Updates

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • Work Schedule A 4/10 work schedule is four (4) ten hour days in a seven (7) day period, for a total of forty (40) hours per week.

  • Project Scope The physical scope of the Project shall be limited to only those capital improvements as described in Appendix A of this Agreement. In the event that circumstances require a change in such physical scope, the change must be approved by the District Committee, recorded in the District Committee's official meeting minutes, and provided to the OPWC Director for the execution of an amendment to this Agreement.

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!