Progress and Scheduling Sample Clauses

Progress and Scheduling. A. Planning, scheduling and progress monitoring are essential functions of the Contractor. Within ten (10) days after the award of the Contract, the Contractor shall prepare and submit for the City a Schedule of Values allocating the Contract Price among the various portions of the Work for purposes of progress payments. The Schedule of Values shall be substantially equivalent to AIA Forms G702 and G703 or as specified by the City. B. The Contractor shall also furnish the City with a Narrative Report corresponding with each monthly update which shall include a description of current and anticipated problem areas, delaying factors and their impact, fragmentary networks (fragment) of delays, and an explanation of corrective action taken or proposed. If the Project is behind schedule in any month, the Contractor's Narrative Report shall indicate precisely what measurements it will take in the next thirty days to put the Work back on schedule. C. The Contractor shall employ and supply a sufficient force of workers, material and equipment, and shall prosecute the Work with such diligence so as to maintain the rate of progress indicated on the Progress Schedule, to prevent work stoppage, and to ensure completion of the Project within the Contract Time. D. The Contractor shall be responsible to prepare, submit and maintain the schedules and Narrative Reports indicated above, and the failure to do so may be considered a material breach of this Contract. Any additional or unanticipated cost or expense required to maintain the schedules shall be solely the Contractor's obligation and shall not be charged to the City.
AutoNDA by SimpleDocs
Progress and Scheduling. 2.3.1 For each project-specific Job Order issued, the Contractor shall prepare and submit to the Owner and the DP a Schedule of Values allocating the Contract Price among the various portions of the Work, by Division, for purposes of progress payments. The Schedule of Values shall be substantially equivalent to AIA Forms G702 and G703 or as specified by Owner. In addition, the Contractor shall submit a construction progress schedule for the Work as part of each Job Order Proposal, in full accordance with the requirements and provisions located in the Contract Documents. 2.3.2 The Contractor shall also furnish the Owner and DP with a Narrative Report corresponding with each monthly update which shall include a description of current and anticipated problem areas, delaying factors and their impact, fragmentary networks (fragnet) of delays, and an explanation of corrective action taken or proposed. If the Project is behind schedule in any month, the Contractor's Narrative Report shall indicate precisely what measures it will take in the next thirty (30) days to put the Work back on schedule. 2.3.3 The Contractor shall be responsible to prepare, submit and maintain the schedules and Narrative Reports indicated above, and the failure to do so may be considered a material breach of this Contract. Any additional or unanticipated cost or expense required to maintain the schedules shall be solely the Contractor's obligation and shall not be charged to the Owner. 2.3.4 The Contractor shall employ and supply a sufficient force of workers, material and equipment, and shall prosecute the Work with such diligence so as to maintain the rate of progress indicated on the Progress Schedule, to prevent work stoppage, and to ensure completion of the Project within the Contract Time. 2.3.5 Upon Owner’s request, as a condition precedent to the release of retained funds, the Contractor shall, after Substantial Completion of the work has been achieved, submit a final Contractor's Construction Schedule which accurately reflects the manner in which the project was constructed and includes actual start and completion dates for all activities on the Construction Schedule. 2.3.6 The date of commencement of the Work under each Job Order is the date established in the Notice to Proceed.
Progress and Scheduling. 2.2.1 The Contractor shall prepare and submit to the Owner and the DP a Schedule of Values allocating the Contract Price among the various portions of the Work, by Division, for purposes of progress payments. The Schedule of Values shall be substantially equivalent to AIA Forms G702 and G703 or as specified by Owner. In addition, upon request by the Owner, Contractor shall submit a construction progress schedule in full accordance with the requirements and provisions located in Section 7 – Payment. 2.2.2 The Contractor shall also furnish the Owner and DP with a Narrative Report corresponding with each monthly update which shall include a description of current and anticipated problem areas, delaying factors and their impact, fragmentary networks (fragment) of delays, and an explanation of corrective action taken or proposed. If the Project is behind schedule in any month, the Contractor's Narrative Report shall indicate precisely what measures it will take in the next thirty days to put the Work back on schedule. 2.2.3 The Contractor shall be responsible to prepare, submit and maintain the schedules and Narrative Reports indicated above, and the failure to do so may be considered a material breach of this Contract. Any additional or unanticipated cost or expense required to maintain the schedules shall be solely the Contractor's obligation and shall not be charged to the Owner. 2.2.4 The Contractor shall employ and supply a sufficient force of workers, material and equipment, and shall prosecute the Work with such diligence so as to maintain the rate of progress indicated on the Progress Schedule, to prevent work stoppage, and to ensure completion of the Project within the Contract Time. 2.2.5 Upon Owner’s request, as a condition precedent to the release of retained funds, the Contractor shall, after Substantial Completion of the work has been achieved, submit a final Contractor's Construction Schedule which accurately reflects the manner in which the project was constructed and includes actual start and completion dates for all activities on the Construction Schedule.
Progress and Scheduling. All times stated in the Contract Documents, including, without limitation, those for the commencement, prosecution and completion of the Work, including agreed upon Milestone Dates as reflected on Attachment 5 to Composite Exhibit “A,” and for the delivery and installation of materials and equipment, are of the essence of the Contract. By executing this Agreement, Contractor confirms that the Contract Time is a reasonable period of time for the performance of the Work. Contractor has provided to Owner and Architect/Engineer a schedule of performance of the Work in conformance with the format of the Progress Schedule defined in Sections 8.2.2 and 8.2.3, showing timely completion of the Work and timely achievement of each milestone date as required by the Contract for Construction and meeting all other requirements of this Article 8 (the “Progress Schedule”). The initial Progress Schedule is attached to the Agreement as Exhibit “G.” Within twenty-one (21) calendar days following Owner’s Notice to Proceed, Contractor shall provide to Owner and Architect/Engineer a proposed updated Progress Schedule. Owner may accept the proposed Progress Schedule as submitted, or reject, noting deficiencies. If such schedule is rejected, the deficiencies noted shall be corrected and a new proposed updated Progress Schedule shall be submitted within ten (10) calendar days. In any case, a complete updated Progress Schedule must be submitted by Contractor prior to any payments being made. If Owner elects to make payment before receiving an acceptable updated Progress Schedule, such action shall not constitute a waiver by Owner to withhold payment in the future pending receipt of a satisfactory updated Progress Schedule or required updates thereto. Once accepted by Owner, the Progress Schedule becomes the controlling Progress Schedule against which all progress shall be measured and updated as required herein. Thereafter, the controlling Progress Schedule and Milestone Schedule can only be changed via executed Xxxxx Order. All schedules and updates are to be provided in print and electronic formats compatible with Owner’s computers and computer software. The Progress Schedule shall be in the form of a network using Critical Path Methodology (“CPM”), clearly showing construction activities, dependencies, and durations. The critical path activities shall be highlighted, float time for non-critical activities shall be shown and the start and stop dates for each activity shall be lis...
Progress and Scheduling 

Related to Progress and Scheduling

  • Dispatch and Scheduling 6.1.1 The SPD shall be entirely responsible to schedule its power as per the applicable regulations / requirements / guidelines of CERC / SERC /SLDC / RLDC or any other competent agency and same being recognized by the RLDC/SLDC or any other competent authority / agency as per applicable regulation/ law / direction and maintain compliance to the applicable Codes/ Grid Code requirements and directions, if any, as specified by concerned SLDC/RLDC from time to time. Any deviation from the schedule will attract the provisions of applicable regulation / guidelines / directions and any financial implication on account of this shall be on the account of the SPD. 6.1.2 The SPD shall be responsible for directly coordinating and dealing with the Buying Entity, State Load Dispatch Centres, Regional Power Committees, and other authorities in all respects in regard to declaration of availability, scheduling and dispatch of power and due compliance with deviation and settlement mechanism and the applicable Grid code Regulations, acknowledging that the SPD and Buying Entity are the Grid connected entities and SECI as an Intermediary Procurer/ trading licensee is not a Grid connected entity in respect of the power contracted under this Agreement. 6.1.3 The SPD shall be responsible for any deviation from scheduling and for any resultant liabilities on account of charges for deviation as per applicable regulations. UI charges on this account shall be directly paid by the SPD. 6.1.4 Auxiliary power consumption will be treated as per the concerned Central/State regulations. 6.1.5 Further, in case of any difference in scheduled energy at the interfaces of all the RLDCs concerned for the corridor of the power flow, including the RLDC of the Buying Entity, SECI will make payments corresponding to the lowest of the individual energy values to the SPD, until rectification of the above error.

  • HOURS OF WORK AND SCHEDULING 15.01 The normal hours of work for an employee are not a guarantee of work per day or per week, or a guarantee of days of work per week. The normal hours of work shall be seven and one-half (7-1/2) hours per day, and seventy-five (75) hours in any bi-weekly period. 15.02 The normal daily shift shall consist of seven and one-half (7 ½) consecutive hours, exclusive of a one-half (1/2) hour unpaid meal period. For employees working the night shift, this one-half (1/2) hour will be paid. Employees shall be entitled to a fifteen (15) minute paid break during each half of the normal daily shift, at a time designated by the Employer. An employee may combine her rest periods in order to have one (1) thirty (30) minute break, providing she has prior approval from the Director of Nursing. When a meal period is interrupted requiring an employee to attend to a work related problem, then the balance of the unused meal period will be taken within two (2) hours of the interruption. If the employee is unable to reschedule such time, she shall be paid time and one-half (1½) her regular straight time hourly rate for all time worked in excess of her normal daily hours, in accordance with Article 16.01. 15.03 Employees required for reporting purposes shall remain at work for a period of up to fifteen (15) minutes which shall be unpaid. Should the reporting time extend beyond fifteen (15) minutes however, the entire period shall be considered overtime for the purposes of payment. 15.04 Requests for change in posted work schedules must be submitted in writing and co-signed by the employee willing to exchange days off or shifts and are subject to the discretion of the Administrator or her designate. In any event, it is understood that such a change initiated by the employee and approved by the Employer shall not result in overtime compensation or payment or any other claims on the Employer by any employee under the terms of this Agreement. 15.05 Where there is a change to Daylight Savings from Standard Time or vice-versa, an employee who is scheduled and works a full shift shall be paid for the actual hours worked at her regular straight time hourly rate. 15.06 There shall be no split shifts. (a) There shall be a minimum of sixteen (16) hours off between changes of shift unless mutually agreed otherwise. (b) An employee shall not be required to work more than seven (7) consecutive days without days off, unless mutually agreed to by the employee and the Employer. (a) Any employee who is working a permanent shift as of December 31, 1996 shall not be transferred to another shift without their consent. (b) Where possible, the employee will not be scheduled to work more than two

  • Recitals and Schedules References to this Agreement include the recitals and schedules which form part of this Agreement for all purposes. References in this Agreement to the Parties are references respectively to the Parties and their legal personal representatives, successors and permitted assigns.

  • Definitions and Schedules 1.1 Words and phrases contained in this Agreement (whether capitalized or not) that are not defined in this Agreement have the meanings given to them in the Electricity Act, 1998, the Ontario Energy Board Act, 1998, any regulations made under either of those Acts, or the Code. 1.2 The following schedules form part of this Agreement: Schedule A – Application and Connection Cost Agreement (recitals) Schedule B – Single Line Diagram, Connection Point and Location of Facilities (section 2.3) Schedule C – List of Other Contracts (section 3.4) Schedule D – Technical and Operating Requirements (section 4.1(d)) Schedule E – Billing and Settlement Procedures (section 5.3) Schedule F – Contacts for Notice (section 12.1) Schedule G – Dispute Resolution (section 16.1) 1) Where a schedule is to be completed by the Parties, the Parties may not include in that schedule a provision that would be contrary to or inconsistent with the Code or the remainder of this Agreement.

  • Exhibits and Schedules The Exhibits and Schedules shall be construed with and as an integral part of this Agreement to the same extent as if the same had been set forth verbatim herein.

  • Clauses and Schedules Any reference in this Agreement to a Clause or a sub-clause or a Schedule is, unless otherwise stated, to a clause or a sub-clause hereof or a schedule hereto.

  • PRE-CONSTRUCTION PHASE SERVICES The Pre-Construction Phase shall be deemed to commence upon the date specified in a written Notice to Proceed with Pre-Construction Phase Services issued by Owner and shall continue through completion of the Construction Documents and procurement of all major Subcontractor agreements. Contractor is not entitled to reimbursement for any costs incurred for Pre-Construction Phase Services performed before issuance of the written Notice to Proceed. Pre-Construction Phase Services may overlap Construction Phase Services. Contractor shall perform the following Pre-Construction Phase Services:

  • Headings and Schedules Headings used herein are not a part of this Agreement and shall not affect the terms hereof. The attached Schedules are a part of this Agreement.

  • Purpose and Scope The purpose of these standard contractual clauses is to ensure compliance with the requirements of Regulation (EU) 2016/679 of the European Parliament and of the Council of 27 April 2016 on the protection of natural persons with regard to the processing of personal data and on the free movement of such data (General Data Protection Regulation)1 for the transfer of personal data to a third country.

  • Records and Schedules of Equipment Each Borrower shall keep accurate and complete records of its Equipment, including kind, quality, quantity, cost, acquisitions and dispositions thereof, and shall submit to Agent, on such periodic basis as Agent may request, a current schedule thereof, in form satisfactory to Agent. Promptly upon request, Borrowers shall deliver to Agent evidence of their ownership or interests in any Equipment.