Execution of the Project Sample Clauses

Execution of the Project. (a) The Borrower declares its commitment to the objectives of the Project as set forth in Schedule 2 to this Agreement, and, to this end, shall carry out the Project with due diligence and efficiency and in conformity with appropriate administrative and financial practices, and shall provide, promptly as needed, the funds, facilities, services and other resources required for the Project. (b) Without limitation upon the provisions of paragraph (a) of this Section and except as the Borrower and the Association shall otherwise agree, the Borrower shall carry out the Project in accordance with the Implementation Program set forth in Schedule 4 to this Agreement. (c) For the purpose of carrying out Parts B.1 and B.2 of the Project, the Borrower shall make part of the proceeds of the Credit available to Participating Financial Institutions under Subsidiary Loan Agreements to be entered into between the Borrower and Participating Financial Institutions, under terms and conditions which shall have been approved by the Association to include those set forth in the Annex to Schedule 4 to this Agreement. (d) The Borrower shall exercise its rights under the Subsidiary Loan Agreements in such manner as to protect the interests of the Borrower and the Association and to accomplish the purposes of the Credit, and, except as the Association shall otherwise agree, the Borrower shall not assign, amend, abrogate or waive the Subsidiary Loan Agreements or any provision thereof. (a) Except as the Association shall otherwise agree, procurement of the goods, services and works required for the Project and to be financed out of the proceeds of the Credit shall be governed by the provisions of Schedule 3 to this Agreement, as said provisions may be further elaborated in the Procurement Plan. (b) The Borrower shall update the Procurement Plan in accordance with guidelines acceptable to the Association, and furnish such update to the Association not later than 12 months after the date of the preceding Procurement Plan, for the Association’s approval. Section 3.03. For the purposes of Section 9.06 of the General Conditions and without limitation thereto, the Borrower shall: (a) prepare, on the basis of guidelines acceptable to the Association, and furnish to the Association not later than six (6) months after the Closing Date or such later date as may be agreed for this purpose between the Borrower and the Association, a plan for the future operation of the Project; and (b) afford t...
AutoNDA by SimpleDocs
Execution of the Project. (a) The Borrower declares its commitment to the objectives of the Project as set forth in Schedule 2 to this Agreement, and to this end shall cause: (i) SDR to coordinate (at the federal level) and issue guidelines related to the carrying out of the Program, to propose annual budgets for such Program and to take all actions necessary to ensure the availability of the counterpart funds for the carrying out of such Program in a timely manner; (ii) SUDENE to coordinate (at the regional level), supervise and monitor the Program; (iii) the Participating Banks, through Participating Agreements, to carry out the credit program included in Parts D and I of the Project; and (iv) EMBRAPA to carry out Part H of the Project, all with due diligence and efficiency, in accordance with appropriate administrative, financial and agricultural practices. (b) Without any limitation or restriction upon any of its other obligations under the Loan Agreement, the Borrower shall cause the State, under contractual arrangements satisfactory to the Bank, to perform in accordance with the provisions of the Project Agreement, all the respective obligations of the State therein set forth, shall take or cause to be taken all action, including the provision of funds, facilities, services and other resources, necessary or appropriate to enable the State to perform its obligations, and shall not take or permit to be taken any action which would prevent or interfere with such performance. (c) Without limitation to its obligations under paragraph (a) above, the Borrower shall: (i) take all action as shall be required to regulate, in a manner satisfactory to the Bank, the funding procedures which will ensure that the Executing Entities shall have the funds required for carrying out the Project available to them in a timely manner; and (ii) provide or cause SUDENE to provide advances in Cruzeiros into: (A) an account opened and operated by EMBRAPA; and (B) an account opened and operated by the State, as referred to in Section 2.01 (h) of the Project Agreement; all in a timely manner and in sufficient amounts for the purpose of financing the activities under Part H of the Project and under the State Project, respectively, as provided in each POA. (d) The Borrower shall make the proceeds of the Loan allocated respectively: (i) for purposes of the State Project available to the State; and (ii) for Part H of the Project available to EMBRAPA; under arrangements satisfactory to the Bank. (e) The Borro...
Execution of the Project. (a) The Borrower declares its commitment to the objectives of the Project as set forth in Schedule 2 to this Agreement, and, to this end, without any limitation or restriction upon any of its other obligations under the Loan Agreement, shall require EG to perform in accordance with the provisions of the Project Agreement all the obligations of EG therein set forth, shall take or cause to be taken all action, including the provision of funds, facilities, services and other resources, necessary or appropriate to enable EG to perform such obligations, and shall not take or permit to be taken any action which would prevent or interfere with such performance. (b) The Borrower shall relend the proceeds of the Loan to EG under a subsidiary loan agreement to be entered into between the Borrower and EG, under terms and conditions which shall have been approved by the Bank, and which shall include, inter alia: (i) maturity of 20 years, with 5-year grace period; (ii) interest rate equal to the Loan rate as specified in Section 2.05 of this Agreement; and (iii) the relending of such proceeds of the Loan by the Borrower and the repayment by EG to be in foreign exchange, with the foreign exchange risk to be borne by EG. (c) The Borrower shall exercise its rights under the Subsidiary Loan Agreement in such manner as to protect the interests of the Borrower and the Bank and to accomplish the purposes of the Loan, and, except as the Bank shall otherwise agree, the Borrower shall not assign, amend, abrogate or waive the Subsidiary Loan Agreement or any provision thereof. Section 3.02. Except as the Bank shall otherwise agree, procurement of the goods and works required for the Project and to be financed out of the proceeds of the Loan shall be governed by the provisions of the Schedule to the Project Agreement. Section 3.03. The Bank and the Borrower hereby agree that the obligations set forth in Sections 9.04, 9.05, 9.06, 9.07, 9.08 and 9.09 of the General Conditions (relating to insurance, use of goods and services, plans and schedules, records and reports, maintenance and land acquisition, respectively) in respect of Part B of the Project shall be carried out by EG pursuant to Section 2.03 of the Project Agreement. Section 3.04. Without limitation upon the provisions of Section 3.01 (a) of this Agreement, during execution of Project, the Borrower shall make available to EG annually on a grant basis the funds that shall have been determined by the Borrower and EG and agre...
Execution of the Project. (a) The Recipient declares its commitment to the objectives of the Project as set forth in Schedule 2 to this Agreement, and, to this end, without any limitation or restriction upon any of its other obligations under this Agreement, shall cause FSRDC to perform in accordance with the provisions of the Project Agreement all the obligations of FSRDC therein set forth, shall take and cause to be taken all action, including the provision of funds, facilities, services and other resources, necessary or appropriate to enable FSRDC to perform such obligations, and shall not take or permit to be taken any action which would prevent or interfere with such performance. (b) The Recipient shall make the proceeds of the Grant available to FSRDC under a subsidiary grant agreement to be entered into between the Recipient and FSRDC, under terms and conditions which shall have been approved by the Association. (c) The Recipient shall exercise its rights under the Subsidiary Grant Agreement in such manner as to protect the interests of the Recipient and the Association and to accomplish the purposes of the Grant, and, except as the Association shall otherwise agree, the Recipient shall not assign, amend, abrogate or waive the Subsidiary Grant Agreement or any provision thereof. (a) Except as the Association shall otherwise agree, procurement of the goods, works and consultants’ services required for the Project and to be financed out of the proceeds of the Grant shall be governed by the provisions of Schedule 1 to the Project Agreement, as said provisions may be further elaborated in the Procurement Plan. (b) The Recipient shall update the Procurement Plan in accordance with guidelines acceptable to the Association, and furnish such update to the Association not later than 12 months after the date of the preceding Procurement Plan, for the Association’s approval. Section 3.03. The Recipient and the Association hereby agree that the obligations set forth in Sections 9.03, 9.04, 9.05, 9.06, 9.07 and 9.08 of the General Conditions (relating to insurance, use of goods and services, plans and schedules, records and reports, maintenance and land acquisition, respectively) shall be carried out by FSRDC pursuant to Section 2.03 of the Project Agreement. Section 3.04. Within six months from the Date of Effectiveness, the Recipient shall have adopted the ESMF, RPF, and the IPDP satisfactory to the Association. Section 3.05. Within six months from the Date of Effectiveness, the Recipi...
Execution of the Project. (a) The Borrower declares its commitment to the objectives of the Project as set forth in Schedule 2 to this Agreement, and, to this end, shall carry out the Project with due diligence and efficiency and in conformity with appropriate administrative, financial, technical, engineering and environmental standards and practices, and shall provide, promptly as needed, the funds, facilities, services and other resources required for the Project. (b) Without limitation upon the provisions of paragraph (a) of this Section and except as the Borrower and the Association shall otherwise agree, the Borrower shall carry out the Project in accordance with the Implementation Program set forth in Schedule 4 to this Agreement and the provisions of the Environmental Management Plan. Section 3.02. Except as the Association shall otherwise agree, procurement of the goods, works and consultants’ services required for the Project and to be financed out of the proceeds of the Credit shall be governed by the provisions of Schedule 3 to this Agreement. Section 3.03. For the purposes of Section 9.06 of the General Conditions and without limitation thereto, the Borrower shall: (a) prepare, on the basis of guidelines acceptable to the Association and furnish to the Association not later than six (6) months after the Closing Date or such later date as may be agreed for this purpose between the Borrower and the Association, a plan for the continued achievement of the objectives of the Project; and (b) afford the Association a reasonable opportunity to exchange views with the Borrower on said plan.
Execution of the Project. Section 3.01. The Borrower declares its commitment to the objectives of the Project as set forth in Schedule 2 to this Agreement, and, to this end, shall carry out the Project with due diligence and efficiency and in conformity with appropriate administrative, technical and financial practices, and shall provide, promptly as needed, the funds, facilities, services and other resources required for the Project. Section 3.02. Except as the Association shall otherwise agree, procurement of the goods and consultants’ services required for the Project and to be financed out of the proceeds of the Credit shall be governed by the provisions of Schedule 3 to this Agreement. Section 3.03. The Borrower shall: (a) maintain policies and procedures adequate to enable it to monitor and evaluate on an ongoing basis, in accordance with indicators satisfactory to the Association, the carrying out of the Project and the achievement of the objectives thereof; (b) prepare, under terms of reference satisfactory to the Association, and furnish to the Association, on or about December 31, 2005, a report integrating the results of the monitoring and evaluation activities performed pursuant to paragraph (a) of this Section, on the progress achieved in the carrying out of the Project during the period preceding the date of said report and setting out the measures recommended to ensure the efficient carrying out of the Project and the achievement of the objectives thereof during the period following such date; and (c) review with the Association, by February 28, 2006, or such later date as the Association shall request, the report referred to in paragraph (b) of this Section, and, thereafter, take all measures required to ensure the efficient completion of the Project and the achievement of the objectives thereof, based on the conclusions and recommendations of the said report and the Association’s views on the matter. Section 3.04. For the purposes of Section 9.06 of the General Conditions and without limitation thereto, the Borrower shall: (a) prepare, on the basis of guidelines acceptable to the Association, and furnish to the Association not later than six (6) months after the Closing Date or such later date as may be agreed for this purpose between the Borrower and the Association, a plan designed to ensure the continued achievement of the Project’s objectives; and (b) afford the Association a reasonable opportunity to exchange views with the Borrower on said plan.
Execution of the Project. (a) The Borrower declares its commitment to the objective of the Project, and, to this end, without any limitation or restriction upon any of its other obligations under the Loan Agreement, shall cause ECTEL to perform in accordance with the provisions of the Project Agreement all the obligations of ECTEL therein set forth, shall take or cause to be taken all action, including the provision of funds, facilities, services and other resources, necessary or appropriate to enable ECTEL to perform such obligations, and shall not take or permit to be taken any action which would prevent or interfere with such performance. (b) The Borrower shall, jointly with the other Participating Countries, enter into a subsidiary loan agreement with ECTEL, under terms and conditions which have been approved by the Bank, for the purposes of governing their respective roles in the carrying out of the Project and making the proceeds of the Loan available to ECTEL. (c) The Borrower shall exercise its rights under the Subsidiary Loan Agreement in such manner as to protect the interests of the Borrower and the Bank and to accomplish the purposes of the Loan, and, except as the Bank shall otherwise agree, the Borrower shall not assign, amend, abrogate or waive the Subsidiary Loan Agreement or any provision thereof. In case of any conflict among the terms of the Subsidiary Loan Agreement and those of this Agreement and/or the Other Loan and Credit Agreements, the terms of this Agreement and/or the Other Loan and Credit Agreements shall prevail. Section 3.02. The Bank and the Borrower hereby agree that the obligations set forth in Sections 9.04, 9.05, 9.06, 9.07, 9.08 and 9.09 of the General Conditions (relating to insurance, use of goods and services, plans and schedules, records and reports, maintenance and land acquisition, respectively) shall be carried out by ECTEL pursuant to Section 2.03 of the Project Agreement.
AutoNDA by SimpleDocs
Execution of the Project. (a) The Borrower declares its commitment to the objectives of the Project as set forth in Schedule 2 to this Agreement, and, to this end, shall carry out the Project through XXXX with due diligence and efficiency and in conformity with appropriate educational, administrative and financial practices, and shall provide, promptly as needed, the funds, facilities, services and other resources required for the Project. (b) Without limitation upon the provisions of paragraph (a) of this Section and except as the Borrower and the Association shall otherwise agree, the Borrower shall carry out the Project in accordance with the relevant provisions of the JFA as applicable, the Operational Manual, the EMP, the VCDP, the EFA Procurement Manual and the Implementation Program set forth in Schedule 4 to this Agreement. (a) Except as the Association shall otherwise agree, procurement of the goods, works and services required for the Project and to be financed out of the proceeds of the Credit shall be governed by the provisions of Schedule 3 to this Agreement, as said provisions may be further elaborated in the Procurement Plan. (b) The Borrower shall update the Procurement Plan in accordance with terms of reference acceptable to the Association, and furnish such update to the Association not later than twelve (12) months after the date of the preceding Procurement Plan, for the Association’s approval. Section 3.03. For the purposes of Section 9.06 of the General Conditions and without limitation thereto, the Borrower shall: (a) prepare, on the basis of guidelines acceptable to the Association, and furnish to the Association not later than six (6) months after the Closing Date or such later date as may be agreed for this purpose between the Borrower and the Association, a plan designed to ensure the continued achievement of the Project’s objectives; and (b) afford the Association a reasonable opportunity to exchange views with the Borrower on said plan.
Execution of the Project. (a) The Borrower declares its commitment to the objectives of the Project as set forth in Schedule 2 to this Agreement, and, to this end, shall carry out the Project with due diligence and efficiency and in conformity with appropriate administrative, educational, and financial practices, and shall provide, promptly as needed, the funds, facilities, services and other resources required for the Project. (b) Without limitation upon the provisions of paragraph (a) of this Section and except as the Borrower and the Bank shall otherwise agree, the Borrower shall carry out the Project in accordance with the Implementation Program set forth in Schedule 5 to this Agreement. Section 3.02. Except as the Bank shall otherwise agree, procurement of the goods, works and consultants’ services required for the Project and to be financed out of the proceeds of the Loan shall be governed by the provisions of Schedule 4 to this Agreement. Section 3.03. For the purposes of Section 9.08 of the General Conditions and without limitation thereto, the Borrower shall: (a) prepare, on the basis of guidelines acceptable to the Bank, and furnish to the Bank not later than six months after the Closing Date or such later date as may be agreed for this purpose between the Borrower and the Bank, a plan designed to ensure the continued achievement of the objectives of the Project; and (b) afford the Bank a reasonable opportunity to exchange views with the Borrower on said plan.
Execution of the Project. (a) The Borrower declares its commitment to the objectives of the Project, and, to this end, without any limitation or restriction upon any of its other obligations under this Agreement, shall, through Fujian Provincial Government, cause Fuzhou to perform in accordance with the provisions set forth in the Project Agreement, shall take or cause to be taken all action, including the provision of funds, facilities, services, and other resources, necessary or appropriate to enable Fuzhou to perform such obligations, and shall not take or permit to be taken any action which would prevent or interfere with such performance. (b) The Borrower shall make available the proceeds of the Loan to Fuzhou, through the Fujian Provincial Government, under terms and conditions satisfactory to the Bank, and the following principal terms: (i) The principal amount shall be made available in Dollars (determined on the date, or respective dates, of withdrawal from the Loan Account) of the value of the currency or currencies so withdrawn. (ii) The following shall be recovered over a period of twenty (20) years, inclusive of a grace period of five (5) years: (A) the principal amount so made available; and (B) an amount equal to the fee paid pursuant to Section 2.04 of this Agreement. (iii) Interest shall be charged on such principal amount withdrawn and outstanding from time to time at a rate equal to the rate of interest applicable from time to time to the Loan pursuant to the provisions of Section 2.06 of this Agreement. (iv) A commitment fee shall be charged on such principal amount of the Loan so made available and not withdrawn from time to time at a rate equal to three fourths of one percent (3/4 of 1%) per annum. (a) Except as the Bank shall otherwise agree, procurement of the goods, works and services required for the Project and to be financed out of the proceeds of the Loan shall be governed by the provisions of Schedule 1 to the Project Agreement, as said provisions may be further elaborated in the Procurement Plan. (b) The Borrower shall, through the Fujian Provincial Government, cause Fuzhou to update the Procurement Plan in accordance with guidelines acceptable to the Bank, and furnish such update to the Bank not later than twelve (12) months after the date of the preceding Procurement Plan, for the Bank’s approval. Section 3.03. The Bank and the Borrower hereby agree that the obligations set forth in Sections 9.04, 9.05, 9.06, 9.07, 9.08 and 9.09 of the General Condi...
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!