CONTRACTOR’S CONSTRUCTION SCHEDULES Sample Clauses
CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 The contractor shall furnish, not later than fifteen (15) days after receipt of "Notice-to-Proceed", a CPM schedule showing the expected times of completion of the various stages of work on this project. The schedule shall be a C.P.M. (Critical Path Method) chart. The work headings therein shall correspond generally with the headings listed in the Contractor's Schedule of Values. Refer to Division 1 - General Requirements. Final times of completion in the schedule shall not exceed the completion date required by the contract Documents. During progress of the work the Contractor shall enter on the schedule that Actual progress at the end of each month, and shall deliver two (2) copies to the Architect along with the Contractor's pay request. Contractor's pay request will not be processed until receipt and review of monthly updated CPM Chart. The schedule shall be cost loaded and be considered in submitting and approving, all progress payments.
3.10.2 The Contractor shall prepare as provided herein and keep current, for the Architect’s approval, a schedule of submittals which is coordinated with the Contractor’s construction schedule and allows the Architect reasonable time to review submittals. The schedule shall be drawn to a time scale and shall indicate the date of commencement and completion of each work item. At a minimum, the schedule shall indicate individual work items for each applicable section of the Specifications, further subdivided as necessary to indicate sitework and each building in the Project. The items shown shall be directly related to the items listed in the approved Schedule of Values required in Paragraph 9.
CONTRACTOR’S CONSTRUCTION SCHEDULES. § 9.8.1 The Contractor, promptly after being awarded the Contract, shall submit for the Owner’s and Architect’s information a Contractor’s construction schedule for the Work. The schedule shall not exceed time limits current
§ 9.8.2 The Contractor shall perform the Work in general accordance with the most recent schedule submitted to the Owner and Architect.
CONTRACTOR’S CONSTRUCTION SCHEDULES. § 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner’s and Architect’s information a Contractor’s construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.
§ 3.10.2 The Contractor shall prepare a submittal schedule, promptly after being awarded the Contract and thereafter as necessary to maintain a current submittal schedule, and shall submit the schedule(s) for the Architect’s approval. The Architect’s approval shall not unreasonably be delayed or withheld. The submittal schedule shall (1) be coordinated with the Contractor’s construction schedule, and (2) allow the Architect reasonable time to review submittals. If the Contractor fails to submit a submittal schedule, the Contractor shall not be entitled to any increase in Contract Sum or extension of Contract Time based on the time required for review of submittals.
§ 3.10.3 The Contractor shall perform the Work in general accordance with the most recent schedules submitted to the Owner and Architect.
CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's and Architect's information a Contractor's construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.
3.10.2 The Contractor shall prepare and keep current, for the Architect's approval, a schedule of submittals which is coordinated with the Contractor's construction schedule and allows the Architect reasonable time to review submittals.
3.10.3 The Contractor shall perform the Work in general accordance with the most recent schedules submitted to the Owner and Architect.
CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the [Owner's and] Architect's information and the Development Manager's and Owner's review and approval a Contractor's construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised as required herein and at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work. The Schedule shall indicate the proposed starting and completion dates for the various subdivisions of the Work as well as the totality of the Work. The schedule shall be updated every thirty (30) days and submitted to Development Manager with Contractor's Applications for Payment. Each schedule shall contain a comparison of actual progress with the estimated progress for such point in time stated in the original schedule. If any schedule submitted sets forth a date for Substantial Completion for the Work or any phase of the Work beyond the Date(s) of Substantial Completion established in the Contract (as the same may be extended as provided in the Contract Documents), then Contractor shall submit to Development Manager and Owner for their review and approval a narrative description of the means and methods which Contractor intends to employ to expedite the progress of the Work to ensure timely completion of the various phases of the Work as well as the totality of the Work. To ensure such timely completion, Contractor shall take all necessary action, including, without limitation, increasing the number of personnel and labor on the Project and implementing overtime and double shifts. In that event, Contractor shall not be entitled to an adjustment in the Contract Sum or the schedule.
3.10.2 The Contractor shall prepare and keep current, for the Development Manager's and Architect's approval, a schedule of submittals which is coordinated with the Contractor's construction schedule and allows the Development Manager and Architect reasonable time to review submittals.
3.10.3 The Contractor shall conform to the most recent schedules.
3.10.4 Prior to execution of this Contract, the Contractor shall have prepared a preliminary project schedule, estimating completion dates for a design, review, approval, bidding, award and construction of the various phases of t...
CONTRACTOR’S CONSTRUCTION SCHEDULES. § 3.10.1 The Project Schedule is attached to the Agreement as an exhibit. The Project Schedule shall not be extended without the prior review and approval of the Owner and the Architect. Contractor acknowledges and agrees that it has prepared and is fully familiar with the Project Schedule, which is a critical element of its Agreement with the Owner, and agrees to be bound thereby.
§ 3.10.1.1 The Contractor shall on each business day prepare a daily force and activity report on a form approved by the Owner which Contractor shall make available for Owner' s review, copying and inspection at all reasonable times.
§ 3.10.2 The Contractor shall prepare a submittal schedule, promptly after being awarded the Contract and shall update the same as necessary to maintain a current submittal schedule, and shall submit the schedule(s) for the Architect’s approval, which shall not unreasonably be delayed or withheld. The submittal schedule shall (1) be coordinated with the Contractor’s construction schedule, and (2) allow the Architect no less than fourteen (14) calendar days to review submittals. If the Contractor fails to submit a submittal schedule, the Contractor shall not be entitled to any increase in Contract Sum or extension of Contract Time based on the time required for review of submittals.
§ 3.10.3 The Contractor shall perform the Work in general accordance with the most recent schedules submitted to the Owner and Architect as required to complete the Work within the Contract Time and as required by the Contract Documents. The schedule for the Work shall be maintained and updated monthly (or more frequently if the Owner reasonably determines that it is necessary) in such form (e.g. bar chart, CPM) and shall contain such information as the Owner and Architect may reasonably request. In addition, if requested by the Owner or Architect, the Contractor shall provide such additional information (such as daily force and activity reports, material purchase and delivery status reports and reports of progress against schedule milestones) as are reasonably necessary to monitor the status of the Work and respond to any delays thereto. Contractor shall also provide Owner with reasonable advance notice, whenever practicable, of the completion of various milestones and or Phases prior to their actual completion (for instance, if Contractor assumes the completion of the then-current phase within the next thirty (30) days, Contractor should specifically apprise the Owner o...
CONTRACTOR’S CONSTRUCTION SCHEDULES. The CM shall provide a copy of the Master Schedule to the bidders. As part of the notice of award of each contract, the CM shall inform each Contractor of the requirements for the preparation of a construction schedule. The Contractor shall prepare its own construction schedule in accordance with the requirements of the Contract Documents. The Contractor's Construction Schedule shall establish completion dates that comply with the requirements of the Master Schedule. The CM shall review each Contractor’s Construction Schedule and shall verify that the schedule is prepared in accordance with the requirements of the Contract Documents and that it establishes completion dates that comply with the requirements of the Master Schedule.
CONTRACTOR’S CONSTRUCTION SCHEDULES. § 3.10.1 The Contractor, shall at the times designated in the Agreement, prepare and submit for the Owner’s and
§ 3.10.2 The Contractor shall at the times designated in the Agreement, prepare a submittal update such schedule as necessary to maintain a current submittal schedule, and shall subm Architect’s approval. The Architect’s approval shall not unreasonably be delayed or withhel shall (1) be coordinated with the Contractor’s construction schedule, and (2) allow the Arch
§ 3.10.3 The Contractor shall perform the Work in general accordance with the most recent approved schedules.
§ 3.10.4 The Contractor shall schedule and conduct progress meetings at the site on a bi-weekly basis (or interval appropriate for the level of job site activity). Attendance is required of each Subcontractor, Supplier, or other entity concerned with current progress or planning future activities. Owner and Architect. shall be notified of meeting dates and times.
CONTRACTOR’S CONSTRUCTION SCHEDULES. 3.10.1. A schedule reflecting the timelines for the components of the Work is attached to the Agreement as Exhibit F. The Schedule shall be revised at appropriate intervals as required by the conditions of the Work and the Project. The schedule (as revised, if applicable) shall not exceed time limits current under the Contract Documents, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work. Unless otherwise provided in the Agreement, the schedule developed under this Subparagraph 3.10.1 shall be for information only and it shall not establish time parameters within which Contractor must complete the Work.
3.10.2. Contractor shall prepare and keep current a schedule of submittals which is coordinated with Contractor's construction schedule and allows the Architect reasonable time to review submittals.
CONTRACTOR’S CONSTRUCTION SCHEDULES. (a) The Contractor shall, immediately after award of the Contract and before submittal of the first Application for Payment, prepare and submit the construction schedule for the Architect/Engineer's and Owner's information, review, and approval in accordance with the following provisions:
(1) Unless otherwise approved in writing by the Owner, the construction schedule shall not exceed the Contract Time limits currently in effect under the Contract Documents and shall provide for expeditious and practicable execution of the Work.
(2) The construction schedule shall include all shop drawing and submittal data requirements, indicating for each:
(i) the latest date to be submitted by the Contractor; and
(ii) the latest date for approval by the Architect/Engineer.
(3) The construction schedule shall be in the form of a critical path management schedule, and shall indicate each critical task (the “predecessor”) of all the major construction activities of the Work in a logical and sequential order (the “project network”) which requires completion prior to commencement of the task next following (the “successor”). Each task shall be identified with:
(i) actual work time, exclusive of slack time, for accomplishment;
(ii) the latest start date;
(iii) the latest finish date;
(iv) the amount of float associated with each task;
(v) the amount of labor, material, and equipment associated with each task; and
(vi) the percentage of completion as of the date of the current schedule.
(4) The construction schedule shall be revised and updated monthly to reflect the actual status of the Work and shall be submitted with each Application for Payment.
(5) On or before the first day of each month, following the date of commencement of the Work as stated in the notice to proceed, the Contractor shall prepare and submit to the Architect/Engineer and the Owner an up-to-date status report of the progress of the various construction phases of the Work in the form of an updated construction schedule. This status report shall consist of a time scale drawing indicating actual progress of the various phases of the Work and the percentage of completion of the entire Work. The original construction schedule shall be updated or changed to indicate any adjustments to the Contract Time granted by the Owner. The updated schedule must be submitted with the Contractor’s Application for Payment. No application will be certified without a satisfactory update to the construction schedule.
(6) The co...