DELAYS AND TIME EXTENSIONS Sample Clauses

DELAYS AND TIME EXTENSIONS a. The Contractor may be granted a time extension if the Contractor encounters an unavoidable delay of the work due to causes completely beyond the Contractor’s control and which the Contractor could not have avoided by the exercise of reasonable care, prudence, foresight and diligence. Causes for which a claim for extension of time may be made include: acts of the public enemy, acts of another contractor in the performance of another contract with the District, priority of a governmental agency for materials or equipment, fire, flood, violent wind storm, epidemic, quarantine restriction, strike, freight embargo, or weather of an unusually severe nature. The Contractor will not be granted time extensions for weather conditions which are normal for the location of the Project, according to the National Weather Service Records. b. A request for extension of time and compensation related thereto shall be made in writing to the Project Manager and District within ten (10) calendar days of the date the delay is encountered, or shall be deemed waived. The request shall include a detailed description of the reasons for the delay and corrective measures by the Contractor. The request shall be accompanied by evidence that the insurance policies required by the Contract shall be in effect during the requested additional period of time. In order for the Project Manager to consider a request for time extension, the Contractor must prove that the reasons stated for the delay actually caused a delay in portions of the work which will result in completion beyond the date specified in the Contract. The Contractor may also be granted a time extension for a significant change in the scope of work which request for extension of time shall be included in a Contract modification proposal. c. No damages or compensation or any kind shall be paid to a Contractor because of delays in the progress of work, whether such delays be avoidable or unavoidable, that are not the responsibility of District. District's liability to Contractor for delays for which District is responsible shall be limited to an extension of time unless such delays were unreasonable under the circumstances involved and were not within the contemplation of the parties when the Contract was awarded. The Contractor shall provide to the District the actual, substantiated costs to Contractor for which the Contractor may claim damages from District. Such costs, if any, shall be directly related to the Project, and sh...
AutoNDA by SimpleDocs
DELAYS AND TIME EXTENSIONS. 25.1 If the Contractor is delayed at any time in the progress of the Work by any act or neglect of the Owner or the DP, or by any separate Contractor employed by the Owner, or by changes in the Work, or by labor disputes, fire, unusual delay in transportation, unusually severe weather conditions, adverse soil conditions, unavoidable casualties, delays specifically authorized by the Owner, or by causes beyond the Contractor's control, avoidance, or mitigation, and without any fault or negligence of the Contractor or Subcontractor or Supplier at any tier, then the Contract Time shall be extended by Change Order for such reasonable time as the Owner may determine that such event has delayed the critical path of the Work or individual milestone or overall completion of the Work after considering the advice of the DP, if the Contractor complies with the notice and documentation requirements set forth below. The Contractor shall pay any additional fees or costs incurred by the Owner or DP as the result of delays caused by the Contractor for circumstances not excused as provided herein. 25.2 Initial notice of any delay in the Work shall be made in writing to the DP and Owner immediately but in no event later than 24 hours after discovery of the event giving rise to the delay. Then, Contractor shall provide additional details of the delay in writing to the DP and the Owner within seven (7) calendar days from the beginning of the delay. Failure to meet these time requirements shall absolutely bar any and all later claims. The detailed notice shall indicate the cause of the delay, the anticipated length of the delay, the probable effect of such delay upon the progress and cost of the Work, and potential mitigation plans. If the cause of the delay is continuing, the Contractor must give written notice every month at the same time it submits the updated progress Narrative Report to the DP. Within fifteen (15) days after the elimination of any such delay, the Contractor shall submit further documentation of the delay and, if applicable, a formal written request covering an extension of time for such delay. The written request for time extension shall state the cause of the delay, the number of days extension requested and provide a fully documented analysis of the Progress Schedule, including a fragnet and any other data demonstrating a delay in the critical path of the Work or individual milestone or the overall project completion. If the Contractor does not comply wi...
DELAYS AND TIME EXTENSIONS. 14.01 If Construction Manager is delayed at any time in the progress of the Work, by any act or omission of Owner or Owner’s other contractors, or by labor disputes, fire, unusually severe weather, unavoidable casualties or other causes beyond Construction Manager’s control, then the date specified for final completion of the Work shall be extended for a number of days equal to the delay; provided that Construction Manager’s written request for such time extension is received by Owner within seven (7) days after the occurrence of such delay to the Work. Delays in delivery shall not be deemed a basis for time extension unless caused by one of the events specifically set forth herein. Notwithstanding any other provision of the agreement between the parties, the Construction Manager shall not be entitled to make any claim for additional costs, including extended overhead, to the extent that the Work is delayed for reasons beyond the control of Owner. 14.02 No extensions will be granted for delays which do not impact the Project critical path and actually cause an extension of the duration of the Work. Construction Manager shall substantiate any extension request with documentation satisfactory to Project Manager; provided, however, that a request for extension or notice of delay given by Construction Manager does not mean that any such request for extension or delay will be granted by Owner.
DELAYS AND TIME EXTENSIONS. 6.2.1 It is agreed that the County’s only liability for any delay from any cause shall be limited to granting a time extension to the Contractor and that no extended general conditions for any delay will be applicable unless agreed to by the County. There is no other obligation, express or implied, on the part of the County to the Contractor for delay from any cause. 6.2.2 The completion time shall be extended when delay in completion of the Work by either the Contractor or the subcontractors is due to any preference, priority or allocation order duly issued by the Federal Government. 6.2.3 Should a dispute arise between the Contractor and the County regarding a delay or time extension, the Contractor shall continue progress on the Work until the dispute is resolved.
DELAYS AND TIME EXTENSIONS. Without limiting the obligations of Contractor set forth in Article 3.2.3, Contractor shall promptly notify Owner in writing of any actual or anticipated event that is delaying or could delay completion of the Facility in accordance with the Work Progress Schedule. Contractor shall indicate the expected duration and anticipated effect of the delay, and the action being taken to correct the problem and make up for lost time. Contractor shall be entitled to an adjustment to the Contract Completion Date and the Target Price, as appropriate, pursuant to the provisions of Article 5 for any delay that may occur, so long as such delay is not caused by Contractor or any Subcontractor or is not otherwise attributable to Contractor's failure to perform in accordance with this Agreement. Contractor shall take all steps reasonably available to Contractor to mitigate any impacts of the delay on the Work Progress Schedule or Reimbursable Costs, as the case may be. All time extensions shall be incorporated into the Contract Documents through the execution of a Change Order.
DELAYS AND TIME EXTENSIONS. Should the Subcontractor's completion of the Work be delayed, hindered, disrupted or otherwise interfered with or made less efficient for any reason beyond the control and without the fault of Subcontractor, and provided such causes would entitle Contractor to an extension of time under the Contract Documents, Subcontractor shall be entitled to a corresponding extension of time for completion of its Work. Provided, however, that Subcontractor's right to an extension of time is expressly conditioned upon Subcontractor's fully complying with the written notice requirements specified herein within three (3) calendar days after the commencement of any delay or disruption, unless a shorter time is required by the Contract Documents. In all events, Subcontractor shall notify Contractor of any delays or disruptions in sufficient time so that Contractor may investigate the claimed delay and timely satisfy its notice requirements with the Owner. Subcontractor's notice shall identify the cause of the delay, the steps being taken by Subcontractor to mitigate the impact of the delay, the work items on the Project critical path affected by the delay, and the estimated effect of the delay on the Subcontractor's completion date. Any request for a time extension based in part on an alleged manpower shortage shall be accompanied with conclusive evidence of the Subcontractor's efforts to obtain necessary manpower and that a manpower shortage in fact exists. Subcontractor's failure to timely and fully comply with each of the above mentioned components of the notice to contractor shall result in a waiver and release of any time extension right to Subcontractor arising out of or in connection with the delay, disruption, or interference. Subcontractor agrees not to make, and hereby waives, any claim for an increase in the Subcontractor price, or for damages or additional compensation, on account of any delay (regardless of extent or nature), hindrance, suspension, disruption, impact, interference (active or otherwise) or other cause which would entitle Subcontractor to an extension of time. A. Subcontractor Delay: Subcontractor acknowledges that it will not be entitled to an extension of time for normal bad weather, or for conditions relating to the accessibility and character of the site, the availability and quality of labor, or for any other cause which could have been identified and taken into account prior to the execution of the Subcontract. Subcontractor shall carry on t...
DELAYS AND TIME EXTENSIONS. 6.3.1 It is agreed that the City's only liability for any delay from any cause shall be limited to granting a time extension to the Contractor and that no extended general conditions for any delay will be applicable unless agreed to by the City. There is no other obligation, express or implied, on the part of the City to the Contractor for delay from any cause.
AutoNDA by SimpleDocs
DELAYS AND TIME EXTENSIONS. 16 ARTICLE 4.......... COMPENSATION............................................................................. 16 4.1...... Compensation........................................................................................................ 16
DELAYS AND TIME EXTENSIONS. The time fixed for the completion of the Work under this Section 5.2 shall only be extended by the number of Days Subcontractor has been delayed, through no fault of Subcontractor, in its performance or completion of the Work by one or more of the following events: a) the act, neglect or default of Owner, Architect, or XYZ; b) delays directly resulting from any fire or other casualty for which Subcontractor is not responsible; c) labor unrest to the extent excusable as a delay by the Prime Contract provisions and, in no way caused by or resulting from the fault or collusion on the part of Subcontractor; d) a lock-out by XYZ; or e) other causes which XYZ determines may justify delay; provided, however, no extension shall be made unless Subcontractor presents to XYZ a written claim for an extension within 48 hours of the commencement of a delay, and under no circumstances shall the time of completion be extended to a date which will prevent XYZ from completing the entire Project within the time allowed XYZ by Owner for that completion. Any such time extension shall be limited to the Days that Subcontractor's overall duration of performance is extended by the foregoing events.

Related to DELAYS AND TIME EXTENSIONS

  • Time Extensions 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

  • Delays and Extensions The CONSULTANT agrees that no charges or claim for damages shall be made by it for any minor delays from any cause whatsoever during the progress of any portion of the Services specified in this Contract. Such delays, if any, shall be compensated for by an extension of time for such period as may be determined by the LPA subject to the CONSULTANT's approval, it being understood, however, that permitting the CONSULTANT to proceed to complete any services, or any part of them after the date to which the time of completion may have been extended, shall in no way operate as a waiver on the part of the LPA of any of its rights herein. In the event of substantial delays or extensions, or change of any kind, not caused by the CONSULTANT, which causes a material change in scope, character or complexity of work the CONSULTANT is to perform under this Contract, the LPA at its sole discretion shall determine any adjustments in compensation and in the schedule for completion of the Services. CONSULTANT must notify the LPA in writing of a material change in the work immediately after the CONSULTANT first recognizes the material change.

  • Delays and Extension of Time If the Contractor is delayed at any time in the progress of providing goods and/or services by an act or neglect of the District, or by changes ordered in the work, or by labor disputes, strikes, insurrections, fire, acts of God; unusual but well documented and excusable delays in performance, or other causes beyond the Contractor’s control, or by delay authorized by the District, then the contract Term of service may be extended by a contract amendment for such reasonable time as the District and the Contractor may agree.

  • Time Extension CONTRACTOR shall provide a time extension request on completion of Task Order for delays caused by others (Permitting Agencies, COUNTY or Contract Cities, or unforeseen conditions such as inclement weather, etc.) and at no fault by CONTRACTOR, subject to approval by COUNTY. COUNTY will review the request and determine in its sole discretion whether the situation warrant a time extension at no-cost or with costs. If CONTRACTOR completes the Task Order beyond the stipulated completion date without COUNTY’s specific written approval for time extension, CONTRACTOR will be subject to liquidated damages and may be construed as non-responsive, which may affect CONTRACTOR for considerations for future Task Orders or projects.

  • Extension of time for completion (i) Without prejudice to any other provision of this Agreement for and in respect of extension of time, the Contractor shall be entitled to extension of time in the Project Completion Schedule (the “Time Extension”) to the extent that completion of any Project Milestone is or will be delayed by any of the following, namely: (a) delay in providing the Right of Way of Construction Zone, environmental clearances or approval of railway authorities, specified in Clause 3.1 (iv); (b) Change of Scope (unless an adjustment to the Scheduled Completion Date has been agreed under Article 13); (c) occurrence of a Force Majeure Event; (d) any delay, impediment or prevention caused by or attributable to the Authority, the Authority's personnel or the Authority's other contractors on the Site; and (e) any other cause or delay which entitles the Contractor to Time Extension in accordance with the provisions of this Agreement. (ii) The Contractor shall, no later than 15 (fifteen) business days from the occurrence of an event or circumstance specified in Clause 10.5 (i), inform the Authority’s Engineer by notice in writing, with a copy to the Authority, stating in reasonable detail with supporting particulars, the event or circumstances giving rise to the claim for Time Extension in accordance with the provisions of this Agreement. Provided that the period of 15 (fifteen) business days shall be calculated from the date on which the Contractor became aware, or should have become aware, of the occurrence of such an event or circumstance. Provided further that notwithstanding anything to the contrary contained in this Agreement, Time Extension shall be due and applicable only for the Works which are affected by the aforesaid events or circumstances and shall not in any manner affect the Project Completion Schedule for and in respect of the Works which are not affected hereunder. (iii) On the failure of the Contractor to issue to the Authority’s Engineer a notice in accordance with the provisions of Clause 10.5 (ii) within the time specified therein, the Contractor shall not be entitled to any Time Extension and shall forfeit its right for any such claims in future. For the avoidance of doubt, in the event of failure of the Contractor to issue notice as specified in this clause 10.5 (iii), the Authority shall be discharged from all liability in connection with the claim. (iv) The Authority’s Engineer shall, on receipt of the claim in accordance with the provisions of Clause 10.5 (ii), examine the claim expeditiously within the time frame specified herein. In the event the Authority’s Engineer requires any clarifications to examine the claim, the Authority’s Engineer shall seek the same within 15 (fifteen) days from the date of receiving the claim. The Contractor shall, on receipt of the communication of the Authority’s Engineer requesting for clarification, furnish the same to the Authority’s Engineer within 10 (ten) days thereof. The Authority’s Engineer shall, within a period of 30 (thirty) days from the date of receipt of such clarifications, forward in writing to the Contractor its determination of Time Extension. Provided that when determining each extension of time under this Clause 10.5, the Authority’s Engineer shall review previous determinations and may increase, but shall not decrease, the total Time Extension. (v) If the event or circumstance giving rise to the notice has a continuing effect: (a) a fully detailed claim shall be considered as interim; (b) the Contractor shall, no later than 10 (ten) days after the close of each month, send further interim claims specifying the accumulated delay, the extension of time claimed, and such further particulars as the Authority’s Engineer may reasonably require; and (c) the Contractor shall send a final claim within 30 (thirty) days after the effect of the event or the circumstance ceases. Upon receipt of the claim hereunder, the Authority’s Engineer shall examine the same in accordance with the provisions of Clause 10.5 (iv) within a period of 30 (thirty) days of the receipt thereof

  • DELAYS AND EXTENSIONS OF TIME 8.3.1 If the Contractor is delayed at any time in the progress of the Work by any act or failure to act by the State or the Architect, or by any employee of either, or by any separate contractor employed by the State, or by changes ordered in the Work, fire, unusual delay in transportation, adverse weather conditions not reasonably anticipatable, unavoidable casualties, or any causes beyond the Contractor's control, or by delay authorized by the State pending alternative dispute resolution proceedings, or by any other cause which may justify the delay, then the Contract Time shall be extended by Change Order for such reasonable time as recommended by the Architect and approved by the State. 8.3.2 Any claim for extension of time shall be made in writing to the Architect not more than twenty days after the commencement of the delay; otherwise it shall be waived. In the case of a continuing delay only one claim is necessary. The Contractor shall provide an estimate of the probable effect of such delay on the progress of the Work. 8.3.3 This Paragraph 8.3 does not exclude the recovery of damages for delay by either party under other provisions of the Contract Documents.

  • Extension of Time Periods The parties may extend any period of time provided in this Article 7 by mutual agreement.

  • Force Majeure Delays In any case where either party hereto is required to do any act (other than the payment of money), delays caused by or resulting from Acts of God or Nature, war, civil commotion, fire, flood or other casualty, labor difficulties, shortages of labor or materials or equipment, government regulations, delay by government or regulatory agencies with respect to approval or permit process, unusually severe weather, or other causes beyond such party’s reasonable control the time during which act shall be completed, shall be deemed to be extended by the period of such delay, whether such time be designated by a fixed date, a fixed time or “a reasonable time.”

  • Contract Extension The City may, in its sole discretion, unilaterally exercise an option to extend the Contract as described in the Contract Documents. In addition, the City may, in its sole discretion, unilaterally extend the Contract on a month-to-month basis following contract expiration if authorized under Charter section 99 and the Contract Documents. Contractor shall not increase its pricing in excess of the percentage increase described in the Contract.

  • Excusable Delays Except with respect to defaults of subproviders, the Engineer shall not be in default by reason of any failure in performance of this contract in accordance with its terms (including any failure to progress in the performance of the work) if such failure arises out of causes beyond the control and without the default or negligence of the Engineer. Such causes may include, but are not restricted to, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather.